Progress of construction as of 05.04.18
Progress of construction as of 05.04.18
5 april 2018
Progress of construction as of 05.04.18

RC “Volodymyrskyi”

Installation of frame structure for 5 floor up to +17,300 – 95%
Installation of frame structure for 6 floor up to +20,300 – 95%
Installation of frame structure for 7 floor up to +23,300 – 95%
Installation of frame structure for 8 floor up to +26,300 – 95%
Installation of frame structure for 9 floor up to +29,300 – 30%
Waterproofing – 0,5%
Installation of anti-lightning system - 0,8%
Installation of internal electric supply networks – 0,3%
Installation of internal low-current networks and smoke exhaust system – 0,3%
Brickworks for internal walls on the basement floor – 82%
Brickworks for external walls on the 1st floor – 90%
Brickworks for internal walls on the 1st floor – 10%
Brickworks for external walls on the 2nd floor – 80%
Brickworks for external walls on the 3d floor – 10,5%
Brickworks for external walls on the 4th floor – 86,72%
Brickworks for internal walls on the 4th floor – 65%

RC “Syretski Sady”

Building No. 1
Section 1: concrete structures of technical premises and parapets on the roof.
Brickworks on the 7th and 10th floors are in progress.
Section 2: concrete pouring of the slab over the 15th floor is completed.
Brickworks on the 8th, 9th and 11th floors are in progress.

Building No. 2
Section 1: works on the slab over the 8th floor are ongoing.

Section 2: works on the slab over the 7th floor are completed.
Section 3: vertical structures of the 7th floor.
Brickworks in the basement have been commenced.

Building No. 3
Excavating works in the pit are completed.

Building No.4
Pouring of the slab over the 6th floor is completed.
Brickworks in the basement are completed.

RC “Yaskravyi”

Building No.6
Installation of monolith frame (2 cranes) – 95.9%
Installation of vent ducts – 68%
Installation of walls, partitions, brickworks (external) – 7.2%
Installation of walls, partitions, brickworks (internal) – 9.9%
Plumbing works – 9.6%
Installation of window structures – 1.7%

Building No. 7
Installation of walls, partitions, brickworks – 91%
Installation of window structures – 94%
Plumbing works – 54%
Electric wiring works – 42%
Ventilation and smoke exhaust systems – 49%
Low-current systems – 46%
Wall plastering – 50%
Arrangement of screed – 40%
Decoration of the general use premises – 15%
Installation of elevators and adjustment works – 40%
Façade works – 10%
Roofing – 35%

RC "Demiivka"

Plumbing works: installation of rises – 99%; installation of water and heat supply piping for the apartments on 1 to 20 floors – 99%; installation of basement networks, pumping station and IHSU -95%. Installation of heating radiators - 70%.
Electric wiring works are ongoing on 1 to 20 floors – 95%. Installation of networks in basement and IHSU is in progress.
Screed: basement – 99%; 1 to 11 floors – 99%; balconies – 80%. Works on 12th floor are ongoing.
Wall plastering: 1-17, 19 floors – 95%, 18, 20 and IHSU – 95%
Ventilation and smoke exhaust systems – installation of ventilation equipment on the roof has been completed; installation of networks in basement is in progress.
Low-current systems – 1-20 floors and in basement – 95%
Installation and adjustment works for elevators: installation of elevators No.1 and No.2.
Installation of window structures – 1-12 floors – 99%
Façade works – installation of heat insulation system for balcony walls in apartments and general facade.
Installation of doors (inclusive fire-proof doors) is completed at the cold passages from 2 to 20 floors and in basement – 80%.
Installation of apartment entrance doors3, 4, 6, 7, 8, 9, 10.
Decoration works inside apartments – laying of tiles and flooring at the premises of general use, basement and on floors 3 to 8, 10 and 11.
Engineering networks: electric wiring – 90%, heat supply – 90%

RC “Parkovi Ozera”

Building No. 12

Installation of walls and partitions – 99%
Installation of window structures – 95%
Plumbing works – 65%
Electric wiring works – 67%
Low-current systems – 47%
Ventilation and smoke-exhaust systems – 36%
Arrangement of screed – 59%
Wall plastering – 78%
Decoration of the general use premises – 22%
Façade installation – 37%
Installation of elevators – 52%
Roofing – 46%
Entrance group– 6%
Construction and assembling works – 37%

Building No. 13
Installation of walls and partitions, brickworks (external) – 52%
Installation of walls and partitions, brickworks (internal) – 35%
Installation of window structures – 22%
Plumbing works – 11%
Electric wiring works – 7%
Brickworks on the roof – 80%

RC "Ozernyi Hai Gatne"

Building No.2

Internal decoration – 92 %
Development of adjoining territory – 95 %

Building No. 3
Façade – 98%
Development of adjoining territory – 95 %

Building No. 4
Roof – 95 %
Façade – 85 %
Internal decoration - 77 %
Development of adjoining territory – 70 %

Building No. 5
Installation of partitions – 97 %
Glazing – 70%

RC “Traditsiya”

Building No.2
Plastering works – 16, 17, 20 floors and on the roof
Plumbing/ electric wiring – 20, 21, 22 floors.
Screed – 11, 14 floors and basement
Puttying – 2-3-4-5-6 floors
Heat insulation of the basement is in progress
Roof – 25%
Façade - 5%
Elevators - 5%

RC “Malakhit”

Building No. 4
Concrete pouring on parapets and roof is ongoing
Brickworks – 11th floor
Section 401 basement - 100 % completed, level – 3.100 (vertical element) – 100%
Works on the basement are completed.
Sections 402-403 – works on the slab over the 8th floor are ongoing.
Brickworks at sections 402-403 level – 3.100 - 100% (works on the ground floor are ongoing).
Installation of window structures (section 404) – 95%
Decoration works in section 404 on the floors 1-2 have been commenced.

RC “Nyvky-Park”

Building No.1

Installation of façade is completed by 99%
Decoration works inside the “turn-key” apartments are in progress.
Development of adjoining territory is in progress
Building No.2
Installation of façade is completed by 99%
Decoration works inside the “turn-key” apartments are in progress.

Building No.3
Brickworks for walls are ongoing: on the floors 14, 15, 16 of sections Г, Д, Ж.
Installation of window structures is in progress at sections Д, on the 11th floor, section Ж – on the 11th floor and section Г – on the 12th floor.
Works on arrangement of external networks are ongoing
Decoration works on basement are in progress
Installation works for elevators in section Ж.
Façade works on the balconies of section Ж on floors 2-8 are ongoing.

Building No.4

Section Е, Б, В – monolith works are completed.
Brickwork of walls: works on the 15, 16, 17 floors of section Е.
Brickwork of walls: works on the 10, 11, 12 floors of section Б, В.
Installation of window structures is in progress at sections Е, Б, В on the 6th and 7th floors.

Building No.5

Installation of monolith frame at section A slab over the 2nd floor, section E – slab over the 1st floor and section Б – vertical basement structures.

Building No.6
Installation of pile field for section Г is ongoing

RC “Vidradnyi”

Building No.2

Roofing is completed for 70%
Plastering works on the 13th and 14th floors are ongoing
Electric wiring and plumbing works are ongoing on the 15th floor are in progress
Brickworks for external walls – 95%
Filling of window openings – 90%
Brickworks on the basement – 90%
Installation of apartment entrance doors and those on the 6th floor is ongoing.

Building No.3
Installation of monolith frame is completed by 90%
Brickworks are ongoing on the 16th and 17th floors.

Building No.4
Reinforcing and pouring of vertical structures on the 17th floor.
Brickworks are ongoing on the floors 12, 14 and 15.

Building No.5
Reinforcing and pouring of the vertical elements of the 14th floor.
Brickworks on the 2nd and 4th floors.

RC “Teremky”

1st stage
Brickworks are completed by 100% up to 25th floor inclusive.
Brickworks on the technical floor are about to be completed.
Completion of Installation of windows up to the 16h floor inclusive.
Installation of windows on the 17th floor is ongoing.
Internal engineering and plumbing works are in progress.
Stage 2, section 2 – slabs over the vertical elements on the 14th floor. Brickworks from the 2nd and up to 6th floor inclusive are ongoing.
Stage 2, section 3 - slab over the vertical elements of the 13th floor is being poured. Brickworks on the floors 2, 3 and 4 are ongoing.
Stage 3 – section 4. Pouring of slabs over the vertical elements of the 2nd floor is completed.
Stage 3- section 5 – Construction works on the basement floor are in progress.
Stage 3- section 6 – Installation of pile field -95%