Progress of construction as of 19.04.18
Progress of construction as of 19.04.18
5 may 2018
Progress of construction as of 05.05.18

RC “Volodymyrskyi”

Installation of frame structure - 5th to 10th floors
Brickworks – basement from 1st to 4th floors
Waterproofing – 0,5%
Installation of anti-lightning system - 0,8%
Installation of internal electric supply networks – 0,35%
Installation of internal low-current networks and smoke exhaust system – 0,35%

RC “Syretski Sady”

Building No. 1
Section 1: concrete structures are completed.
Brickworks on the 12th floor + brickworks on the roof (light aerated concrete).
Windows -2-4 floors (w/o balconies)
Section 2: concrete structures are completed.
Brickworks on the 12th floor are in progress (light aerated concrete).
Windows -2-4 floors (w/o balconies)

Building No. 2
Section 1: floor and ceiling slab over the 10th floor is completed.
Brickworks – 2nd floor (ceramic blocks)
Section 2: Installation of vertical structures on the 11th floor
Brickworks: - 2-3 floors (ceramic blocks)
Section 3: Installation of vertical structures on the 10th floor.
Brickworks – 1st floor (ceramic blocks).

Building No. 3
Basement slab is in progress below section 2.

Building No.4
Installation of vertical structures on the 7th floor is in progress.
Brickworks – 1st floor (ceramic blocks).

RC “Yaskravyi”

Building No.6
Installation of monolith frame (2 cranes) – 98.2%
Installation of vent ducts – 98%
Installation of walls, partitions, brickworks (external) – 17.3%
Installation of walls, partitions, brickworks (internal) – 13.1%
Plumbing works – 12.4%
Installation of window structures – 6.8%
Electric wiring works – 1.5%

Building No. 7
Installation of walls, partitions, brickworks – 96%
Installation of window structures – 95%
Plumbing works – 59%
Electric wiring works – 48%
Ventilation and smoke exhaust systems – 55%
Low-current systems – 51%
Wall plastering – 61%
Arrangement of screed – 48%
Decoration of the general use premises – 22%
Installation of elevators and adjustment works – 52%
Façade works – 23%
Roofing – 45%
Brickworks on the roof – 1%

RC "Demiivka"

Plumbing works: – 1st to 20th floors.
Installation of heating radiators - 80%.
Screed: basement, 1st to 14th floors, balconies
Wall plastering: basement, IHSU, 1st to 20th floors.
Ventilation and smoke exhaust systems – installation of ventilation equipment on the roof and in basement has been completed;
Low-current systems – 1st to 20th floors and in basement.
Installation of elevators: No.1 and No.2.
Installation of window structures – 1st to 12th floors
Installation of heat insulation system for balcony walls in apartments and general facade.
Installation of doors: 2nd to 20th floors and in basement.
Decoration works inside apartments – laying of tiles and flooring at the premises of general use, basement and on floors 2th to 13th.
Engineering networks: electric wiring – 95%, heat supply – 95%

RC “Parkovi Ozera”

Building No. 12

Installation of walls and partitions – 99%
Installation of window structures – 95%
Plumbing works – 71%
Electric wiring works – 72%
Low-current systems – 65%
Ventilation and smoke-exhaust systems – 53%
Arrangement of screed – 74%
Wall plastering – 91%
Decoration of the general use premises – 36%
Façade installation – 41%
Installation of elevators – 55%
Roofing – 46%
Entrance group– 18%
Construction and assembling works – 59%

Building No. 13
Installation of walls and partitions, brickworks (external) – 78%
Installation of walls and partitions, brickworks (internal) – 55%
Installation of window structures – 54%
Plumbing works – 22%
Electric wiring works – 11%
Wall plastering – 2%
Entrance group – 7%

RC "Ozernyi Hai Gatne"

Building No.2
Internal decoration – 95 %
Development of adjoining territory – 95 %

Building No. 3
Façade – 98%
Development of adjoining territory – 95 %

Building No. 4
Roof – 95 %
Façade – 85 %
Internal decoration - 80 %
Development of adjoining territory – 80%

Building No. 5
Installation of partitions – 97%
Glazing – 75%

Building No.6
Ground excavation is completed

RC “Traditsiya”

Building No.2
Plastering works – 23nd floor and on the roof
Plumbing/ electric wiring – 25th floor.
Screed – 17th floor.
Puttying – 6th to 11th floors
Roof – 70%
Façade - 45%
Elevators - 50%
Tiling in corridors – from 11th to 12th floor
Decoration works – 3d to 4 th floors
Pumping station and IHSU – 10%

RC “Malakhit”

Building No. 4
Section 405-406 – monolith frame -100%
Brickworks – 13th floor
Section 401 basement - 100 %, floor and ceiling slab of the 2nd floor is in progress.
Sections 402-403 – works on the slab over the 8th floor are completed.
Brickworks at sections 402-403 works on the 5th floor are ongoing.
Installation of window structures: Section 404 – 95%, section 405 -406 – 45%
Decoration works at section 404 on the floors 1-6.
Section 405 – 1st floor

RC “Nyvky-Park”

Building No.1
Installation of façade - 99%
Decoration works inside the “turn-key” apartments are in progress.
Development of adjoining territory is in progress.
Installation of brackets for air-conditioners is in progress

Building No.2
Installation of façade - 99%
Decoration works inside the “turn-key” apartments are in progress.
Installation of brackets for air-conditioners is in progress

Building No.3
Brickworks for walls; works are completed except the locations where protruding platforms have been installed.
Installation of window structures is in progress at sections Д, on the 12th floor, section Ж – on the 14th floor and section Г – on the 12th and 13th floors.
Works on arrangement of internal mains are ongoing.
Decoration works at general use premises at sections Г and Д on 2nd to 14th floors are in progress
Installation works for elevators in section Ж, Г and Д.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Roofing is in progress.
Installation of screed at sections Г and Д on the 3d floor is ongoing.

Building No.4
Monolith works at sections Е, Б and B are completed.
Brickworks for walls: works on section E are completed except the locations where protruding platforms have been installed. Works on 11th, 12th 13th and 14th floors at section Б and B are ongoing.
Installation of window structures is in progress in sections Е, Б, В on the 9th and 10th floors.
Installation of external mains is in progress.
Installation of entrance groups is ongoing
Decoration works on the basement are in progress

Building No.5
Installation of monolith frame
section A vertical structures of the 5th floor,
section E – slab over the 4th floor
section Б – slab over the 2nd floor.

Building No.6
Installation of vertical elements of the basement at section Г
Pouring of concrete at section Е is ongoing.
Installation of pile field at section Д.
Installation of tower crane.

RC “Vidradnyi”

Building No.2
Roofing works - 70%
Plastering works on the 15th and 16th floors are ongoing
Electric wiring and plumbing works – 9th floor
Filling of window openings – 90%
Installation of cement and sand screed on the 9th floor.
Façade works.
Tiling works on the 6th and 7th floors.
Decoration works on floors 6, 8, 10 and 11 are ongoing.

Building No.3
Installation of monolith frame - 90%
Brickworks are ongoing on the 16th.
Roofing works are ongoing.

Building No.4
Installation of monolith frame - 90%
Brickworks are ongoing on the floors 14, 15 and 16.

Building No.5
Reinforcing and pouring of vertical elements of the 15th floor.
Brickworks on the floors 2 to 10.

RC “Teremky”

1st stage
Brickworks for vent ducts on the roof are ongoing.
Installation of windows on 21st and 22nd floors is in progress.
Internal engineering and plumbing works are in progress. Electric wiring works inside the building are in progress (3d and 4th floors).
Plastering works inside the turn-key apartments on 3d and 4th floors are ongoing.
Stage 2, section 2 – slab over the vertical elements on the 15th floor is completed.
Slab over the vertical elements on the 16th floor is in progress.
Brickworks on the 7th and 10th floors are ongoing.
Stage 2, section 3 - slab over the vertical elements of the 16th floor is in progress.
Brickworks on the 5th to 8th floors are ongoing.
Stage 3 – section 4. Pouring of slabs over the vertical elements of the 4th floor is ongoing.
Stage 3- section 5 – Construction works for vertical elements on the 2nd floor.
Stage 3- section 6 – reinforcement of the basement is in progress