Progress of construction as of 07.02.18
Progress of construction as of 07.02.18
7 february 2018

Progress of construction as of 07.02.18

RC “Volodymyrskyi”  

Installation of frame structure for 5 floor up to +17,300 – 95% 
Installation of frame structure for 6 floor up to +20,300 – 95%
Installation of frame structure for 7 floor up to +23,300 – 70%
Installation of frame structure for 8 floor up to +26,300 – 2%
Waterproofing – 0,5%
Installation of anti-lightning system - 0,07%
Installation of internal electric supply networks – 0,1%
Installation of internal low-current networks and smoke exhaust system – 0,09%
Brickworks on the basement floor – 82%
Brickworks on the 1st floor – 40%
Brickworks on the 2nd floor – 47%
Brickworks on the 3d floor – 5,5%
Brickworks on the 4th floor  – 45%

RC “Syretski Sady” 

Building No.1
Section 1: vertical structures on 12th floor are in progress.
Brickworks on the 4th floor have been commenced.
Section 2: vertical structures on 12th floor are completed.
Brickworks on the 4th floor have been commenced.

Building No. 2
Section 1: vertical structures on 3d floor are completed.
Section 2: floor and ceiling slab of the 3d floor is completed.
Section 3: vertical structures on 3d floor have been commenced.

Building No. 3
Cleaning of territory is completed.

Building No.4
floor and ceiling slab of the 2nd floor and vertical structures on the 3d floor are in progress.

RC “Yaskravyi”  

Building No.6
Installation of monolith frame (2 cranes) – 77,3 %
Installation of vent ducts – 44,9%

Building No. 7 
Installation of walls, partitions, brickworks – 70%
Installation of window structures – 69%
Plumbing works – 47%
Electric wiring works – 36%
Ventilation and smoke exhaust systems – 38%
Low-current systems – 37%
Wall plastering – 28%
Arrangement of screed – 29%
Installation of elevators and putting into operation – 12%
Installation of facades – 3%
Roofing – 35%

RC "Ozernyi Hai Gatne"

Building No.2
Facade – 95 %
Internal decoration – 90 %
Development of adjoining territory – 95 %

Building No. 3
Facade – 98%
Development of adjoining territory – 95 %

Building No. 4
Roof – 85 %
Facade – 85 %
Internal decoration - 75 %
Development of adjoining territory – 70%

Building No.5 
Installation of ceilings – 95 % (10th floor)
Installation of monolith floor and ceiling slabs – 95 %
Installation of partitions – 90 %

RC "Demiivka"  

Building No.2
Plumbing works: installation of rises – 95%; installation of water and heat supply piping for the apartments on 2 to 20 floors – 95%; installation of basement networks, pumping station and IHSU.
Electric wiring works are ongoing on 2 to 20 floors – 95%
Screed: basement – 99%; 3 to 8 floors – 99%; balconies – 80%
Wall plastering works  – 95%
Ventilation and smoke exhaust systems –installation of the network in basement
Installation of window structures – 12-20 floors – 99%
Installation of doors (inclusive fireproof doors) is completed at the cold passages from 2 to 15 floor and in basement – 80%
Installation and erection of elevators – delivery of equipment and installation of cargo elevator.
Low-current systems – 2-17 floors – 95%
Engineering networks: electric wiring – 90%, heat supply – 20%  

RC “Parkovi Ozera” 

Building No. 12
Installation of walls and partitions – 93%
Installation of window structures – 74%
Plumbing works – 51%
Electric wiring works – 37%
Low-current systems – 26%
Ventilation and smoke-exhaust systems – 30%
Arrangement of screed – 39%
Plastering works – 59%
Decoration of general use premises – 16%
Installation of elevators – 19%
Roofing – 46%
Entrance – 6%
Construction and installation works – 37%

Building No. 13
Installation of monolith frame – 96%
Installation of walls and partitions – 19%

RC “Traditsiya”

Building No. 2
Brickworks are ongoing on 26-28 floors.
Installation of window structures on 19-21 floors;
Plastering works – 8-11 floors;
Plumbing/ electric wiring – 6-11 floors.
Arrangement of screed at the level of the 2nd floor.

RC “Malakhit”

Building No. 4
Installation of vertical reinforced concrete structures at sections 405-406 are ongoing – slab of the 9th floor.
Brickworks are ongoing from 3 to 6 floor.
Section 401 basement - 100 %, level – 3.100
Section 402-403 – vertical element of the 4th floor.

RC “Nyvky-Park” 

Building No.1
Installation of façade is completed by 99%
Erection and adjustment of elevators – regulation of stops.

Building No.2
Installation of façade is completed by 96%
Erection and adjustment of elevators – regulation of stops.

Building No.3:
Section Г: works related to installation of slabs over the machine operation premises are in progress.
Brickwork of walls: works on the 12-14 floors at sections Г, Д, Ж.
Installation of window structures is in progress at sections Г, Д, Ж and 4th floor.

Building No.4:
Sections Е, Б, В: installation of monolith frame of the 17th floor.
Brickwork of walls: works on the 7-10 floors at sections Е, Б, В.
Installation of window structures is in progress at sections Е, Б, В and 2nd floor.

Building No.5:
Installation of the pile field for section Б is ongoing.
Installation of vertical elements of the basement at section А is in progress.

Building No.6:
Installation of test piles is ongoing.

RC “Vidradnyi” 

Building No.2 
Roofing is completed for 70%
Plastering works on the 8th floor are ongoing
Electric wiring and plumbing works are ongoing on the 9th floor
Brickworks for external walls are completed by 95%
Filling of window openings is completed by 90%
Brickworks on the basement are completed by 90%
Installation of doors for technical premises and on third floor has been commenced.

Building No.3
Installation of monolith frame is completed by 90%
Brickworks are ongoing on 9, 13, 14, 15 and 16 floors.

Building No.4
Reinforcing and pouring of vertical structures on the 15th floor
Brickworks are ongoing on 6, 7, 8 and 10 floors.

Building No.5
Reinforcing and pouring of the slab over the 7the floor.

RC “Teremky” 

I stage – installation of the slab over the technical floor is in progress.
Brickworks are completed by 100% and up to the 20th floor. Brickworks on 21 to 24 floors are ongoing.
Windows are installed up to the 6th floor inclusive. Installation of windows on 7 to 9 floors is in progress.
II stage, Section 2 – slab over the 8th floor is completed.
II stage, Section 3 – installation of slabs over the vertical elements on the 8th floor is ongoing.
III stage – pile works at section 4 are completed.