Progress of construction as of 07.03.18
Progress of construction as of 07.03.18
7 march 2018
Progress of construction as of 07.03.18

RC “Volodymyrskyi”

Installation of frame structure for 5 floor up to +17,300 – 95%  
Installation of frame structure for 6 floor up to +20,300 – 95%
Installation of frame structure for 7 floor up to +23,300 – 95%
Installation of frame structure for 8 floor up to +26,300 – 45%
Waterproofing – 0,5%
Installation of anti-lightning system - 0,6%
Installation of internal electric supply networks – 0,15%
Installation of internal low-current networks and smoke exhaust system – 0,09%
Brickworks on the basement floor – 82%
Brickworks for external walls on the 1st floor – 90%
Brickworks for internal walls on the 1st floor – 10%
Brickworks for external walls on the 2nd floor – 80%
Brickworks for external walls on the 3d floor – 10,5%
Brickworks for external walls on the 4th floor – 86,72%
Brickworks for internal walls on the 4th floor – 65%
Installation of internal electric supply networks – 0,2 %
Installation of internal low-current networks and  smoke exhaust system – 0,2%

RC “Syretski Sady”

Будинок № 1
Section 1: concrete structures: slab over the 14th floor is in progress.
Brickworks on the 6th floor are in progress.
Section 2: concrete pouring of the slab over the 14th floor is commenced.
Brickworks on the 6th floor are in progress.

Building No. 2
Section 1: slab over the 5th floor is completed.
Section 2: vertical structures on 6th floor are in progress.
Section 3: slab over the 4th floor is in progress.
Brickworks in the basement have been commenced.
Building No. 3
Clearing of territory is completed.

Building No.4
Slab over the 4th floor is completed.

RC “Yaskravyi”

Building No.6
Installation of monolith frame (2 cranes) – 86%
Installation of vent ducts – 60,3%
Installation of walls, partitions, brickworks (external) – 4,3%
Installation of walls, partitions, brickworks (internal) – 2,4%
Plumbing works – 3,6%

Building No. 7  
Installation of walls, partitions, brickworks – 81%
Installation of window structures – 76%
Plumbing works – 51%
Electric wiring works – 39%
Ventilation and smoke exhaust systems – 46%
Low-current systems – 42%
Wall plastering – 33%
Arrangement of screed – 32%
Arrangement of the general use premises – 13%
Installation of elevators and adjustment works – 27%
Façade works – 4%
Roofing – 35%

RC "Demiivka"

Plumbing works: installation of rises – 95%; installation of water and heat supply piping for the apartments on 1 to 20 floors – 95%; installation of basement networks, pumping station and IHSU.
Electric wiring works are ongoing on 1 to 20 floors – 95%. Installation of networks in basement and IHSU is in progress.
Screed: basement – 99%; 3 to 9 floors – 99%; balconies – 80%
Wall plastering – 95%
Ventilation and smoke exhaust systems – installation of ventilation equipment on the roof has been completed; installation of networks in basement is in progress.
Installation of window structures – 1-12 floors – 99%
Installation of doors is completed at the cold passages from 2 to 15 floor and in basement – 80% Installation of apartment entrance doors is in progress.
Installation and erection of elevators: delivery of equipment and installation of elevators No.1 and No.2.
Low-current systems – 1-20 floors and in basement – 95%
Engineering networks: electric wiring – 90%, heat supply – 20%

RC “Parkovi Ozera”

Building No. 12
Installation of walls and partitions – 99%
Installation of window structures – 95%
Plumbing works – 57%
Electric wiring works – 48%
Low-current systems – 28%
Ventilation and smoke-exhaust systems – 30%
Arrangement of screed – 52%
Wall plastering – 63%
Decoration of general use premises – 19%
Installation of elevators – 30%
Roofing – 46%
Entrance group– 6%
Construction and assembling works – 37%

Building No. 13
Installation of monolith concrete frame – 99%
Installation of walls and partitions, brickworks (external)  – 37%
Installation of walls and partitions, brickworks (internal) – 29%
Installation of window structures – 7%
Plumbing works – 2%
Brickworks on the roof – 74%

RC "Ozernyi Hai Gatne"

Building No.2
Roof – 95%
Facade – 95 %
Internal decoration – 90 %
Development of adjoining territory – 95 %

Building No. 3
Roof – 95 %
Façade – 98%
Development of adjoining territory – 95 %

Building No. 4
Roof – 83 %
Façade – 83 %
Internal decoration - 79 %
Development of adjoining territory – 70 %

Building No. 5
Installation of walls – 95 % (10th floor).
Installation of monolith slabs – 95 %
Installation of partitions – 92 %

RC “Traditsiya”

Building No. 2
Brickworks are completed.
Installation of window structures on 23-25 floors;
Plastering – 8-11 floors;
Plumbing/ electric wiring – 14-17 floors.
Screed on the level of the 7th floor.

RC “Malakhit”

Building No. 4
Installation of vertical reinforced concrete structures at sections 405-406 are ongoing – slab over the 11th floor.
Brickworks are ongoing from 3 to 7 floors.
Section 401 basement is completed by100 %, level – 3.100
Works on the basement are ongoing.
Sections 402-403 – vertical element of the 8th floor.

RC “Nyvky-Park”  

Будинок №1
Building No.1
Installation of façade is completed by 99%

Building No.2
Installation of façade is completed by 96%
Erection and adjustment of elevators – regulation of stops.

Building No.3
Brickworks for walls are ongoing: on the floors 12, 13, 14, 16 of sections Г, Д, Ж.
Installation of window structures is in progress at sections Д, on the 6th floor, section Ж – on the 8th floor and section Г – on the 10th floor.

Building No.4:
Sections Е, В installation of floor and ceiling slabs over the elevator machine premises are in progress.
Section В – installation of monolith parapet.
Brickwork of walls: works on the 9,10,11,12 floors of sections Е, Б, В.
Installation of window structures is in progress at sections Е, Б, В on 4,5 floors.

Building No.5
Arrangement of basement under layer at section Е is in progress.
Reinforcing of foundation frame at section Б is ongoing.

Building No.6
Installation of test piles is ongoing.

RC “Vidradnyi”

Building No.2  
Roofing is completed for 70%
Plastering works on the 13th and 14th floors are ongoing
Electric wiring and plumbing works are ongoing on the 13th and 14th floors are in progress
Brickworks for external walls – 95%
Filling of window openings – 90%
Brickworks on the basement – 90%
Installation of apartment entrance doors and those for technical premises is ongoing.

Building No.3
Installation of monolith frame - 90%
Brickworks are ongoing on 15th and 16th floors.

Building No.4
Reinforcing and pouring of vertical structures on technical floor.
Brickworks are ongoing on 1, 6, 7, 9, 10, 11, 12 and 13 floors.

Building No.5
Reinforcing and pouring of the slab over the 9th floor.

RC “Teremky”

I stage
Brickworks are completed by 100% on 24th floor. 25th floor is currently being completed..
Installation of window structures on the 11 floor is completed. Installation of windows is about to be completed on the 12th floor.
2 stage, section 2 - slab over the 9th floor is completed. Installation of slab over the vertical elements on the 10th floor is completed. Brickworks on the 2nd and 3d floors are ongoing.
2 stage, section 3 - slab over the 9th floor is completed. Installation of slab over the vertical elements on the 10th floor is completed. Brickworks on the 2nd and 3d floors are ongoing.
3 stage – pile field at section 4 is installed. Monolith works on the basement are in progress.
section 5 – installation of piles is ongoing.