Progress of construction as of 12.01.18
Progress of construction as of 12.01.18
12 january 2018

Progress of construction as of 12.01.18

RC “Volodymyrskyi”
Installation of frame of the 5th floor at the level +17.300 – 95% 
Installation of frame of the 6th floor at the level +20.300 – 65%
Waterproofing – 0.5%
Installation of lightning protection system - (0.07%)
Internal electric wiring network – commenced (0.07%)
Brickwork at the ground floor – 82%
Brickwork at the first floor – 40%
Brickwork at the second floor – 47%
Brickwork at the third floor – 5.5%
Brickwork at the third floor – 19%  

RC “Syretski Sady”  

Building No. 1
Section 1: concrete pour for walls and pylons over 9th floor;
Brickworks on 2nd and 3d floors have been commenced
Waterproofing – 85%
Section 2: ceiling and floor slab over the 8th floor is completed
Brickworks on 1st and 2nd floors have been commenced
Waterproofing 85%

Building No. 2
Section 1: ceiling and floor slab over the 1st floor is completed;
Section 2: slab over the 1st floor is completed;
Section 3: slab over the basement is completed.

Building No. 3
Clearing of the territory is completed.

Building No.  4
Slab over the basement is completed  

RC “Yaskravyi” 

Building No.6
Installation of the main pile field (installation of test bushes is not included) – 100%
Installation of the basement slab – 100%
Installation of the monolith frame (while installing 2 cranes) – 54%
Installation of ventilation ducts – 33%

Building No. 7
Installation of the main pile field (installation of test bushes is not included) – 100%
Installation of the basement slab – 100%
Installation of the monolith frame (while installing 3 cranes) – 100%
Installation of walls, partitions, brickwork – 67%
Installation of ventilation ducts – 100%
Installation of window structures – 57%
Plumbing works– 43%
Electric installation works – 32%
Ventilation and smoke exhaust systems – 35%
Low-current system – 33%
Wall plastering – 25%
Screed – 26%
Installation of elevators and erection works – 7%
Brickwork on the roof – 100%
Roofing – 35%  

RC “Ozernyi Hai Gatne”  

Building No. 2
Installation of the basement – 100%
Waterproofing of the walls of the ground floor – 100%
Installation of walls – 100% (brickwork of the mansard floor).
Installation of monolith ceiling and floor slabs– 100%
Installation of partitions – 100%
Roofing – 95%
Façade – 95 %
Internal finishing works – 85 %
Development of the adjoining territory – 90 %

Building No. 3
Installation of the basement – 100 %
Waterproofing of walls of the ground floor – 100 %
Installation of walls – 100 %
Installation of monolith ceiling and floor slabs – 100 %
Installation of partitions – 100 %
Roofing – 95 %
Façade  – 95%
Development of the adjoining territory – 80 %

Building No. 4
Installation of the basement is completed – 100 %
Waterproofing of the ground floor is completed 100 %
Installation of walls – 100% 
Installation of monolith ceiling and floor slabs – 100%
Installation of partitions – 100%
Roofing – 60%
Façade  – 80 %
Internal finishing works - 60 %
Development of the adjoining territory – 40 %

Building No. 5
Installation of basement – 100 %
Waterproofing of the ground floor is completed 100 %
Installation of ceilings – 90 % (9th floor).
Installation of monolith ceiling and floor slab– 85 %
Installation of partitions – 75 %  

RC “Demiivka” 

On the roof: works on the arrangement of parapets and reinforced concrete structures for machine rooms are completed.
Installation of ventilation blocks completed.
Installation of stairwells completed.
Installation of water supply rises, heating and domestic sewage pipes is ongoing– 95%
Readiness of monolith structures of entrances– 100 %
Floor screed: basement -50%, 3d to 8th floor – 99%, balconies – 80%.
Wall plastering – 95%
Completion of Installation of windows up to the 12th.
Installation of windows at 19-20-floors is ongoing – 75%
Low-current systems – 2-15 floors – 95%
Roofing – 100%
Installation of horizontal piping of heating and water supply systems: 95%
Electrical works: 2-16 floors – 90%
Heating and water supply systems are completed in zones 1 and 2.
Domestic sewage- 100%
Installation of rises (vertical) - 100%
Engineering networks: wiring – 90%, heating – 20%  

RC "Parkovi Ozera"  

Building No.11
Installation of external walls and partitions (brickwork) – 100%
Installation of internal walls and partitions – 100% 
Roofing – 100%
Installation of window structures – 100%
Installation of facades – 100%
Plastering of walls – 100% 
Plumbing works – 89%
Floor screed – 100%
Installation of the system of internal mains – 95%
Low-current systems – installation of electric meters are being completed -96 %
Ventilation and smoke exhausting – 97 %
Installation of elevators – 93 %
Engineering networks – 96%
Development of the territory – 100%
Finishing works – 100%

Building No.12
Installation of monolith frame – 100%
Installation of walls and partitions – 85%
Arrangement of ventilation ducts – 100%
Installation of window structures – 67%
Plumbing works – 48%
Electric wiring works – 37%
Low-current systems – 23%
Ventilation and fume exhaust systems – 19%
Arrangement of screed – 36%
Wall plastering – 53%
Decoration of the common use areas – 15%
Installation of elevators – 7%
Brickworks on the roof – 100%

Building No. 13
Installation of the basement slab – 100% 
Installation of monolith frame – 95%
Installation of walls and partitions – 13%
Installation of ventilation ducts – 93%
    
RC “Traditsiya”

Installation of ceiling and floor slabs 100%
Brickworks are in progress on 24-26 floors and roof.
Installation of window structures on12-13 floors.
Plastering works – 7-8 floors.
Plumbing/ electric works – 6-7 floors.  
  
RC “Malakhit” 

Monolith frame, section 404 – 100 %
Brickworks on the first and sixth floors, section 404 – 100%
Installation of vertical reinforced concrete structures are in progress in sections 405-406 – 7th floor.
Brickwork on floors 1 to 4.
Parking lot П1 – installation of monolith ceiling and floor slabs 100%
Parking lot П2 - installation of monolith ceiling and floor slabs 100%
Section 401 basement - 100 %, level – 3.100
Section 402-403 – concrete pour on vertical elements of the second floor.  

RC “Nyvky-Park”

Building No.1
Installation of monolith frame is completed.
Installation of walls and partitions is completed.
Installation of window structures is completed.
Installation of internal engineering networks is in progress.
Floor screed, plastering are completed.
Internal finishing works in premises are in progress:
Installation of doors is completed.
Installation of the façade is completed for 98%
Start-up and adjustment works for elevators are in progress
Installation of steel structures at entrances is in progress.
Installation of external engineering networks is ongoing.
Works on development of the court yard are in progress.

Building No.2
Installation of the monolith frame is completed.
Installation of walls and partitions is completed.
Installation of window structures is completed.
Works on installation of internal engineering networks are in progress.
Floor screed and plastering works are completed.
Installation of doors is completed.
Works on decoration of internal premises:
Works on start-up and adjustment of elevators are in progress.
Façade finishing works are completed for 90%
Works on development of the court yard are in progress.

Building No.3
Sections Г, Д, Ж: works on installation of monolith frame for parapets are in progress.
Brickworks of walls: works on 10-12 floors, sections Г, Д, Ж are in progress.
Commenced to installation of window structures on sections Г, Д, Ж.

Building No.4
Sections Е, Б, В works on installation of monolith frame of the 15th floor are in progress.
Brickworks of walls: works on 6-8 floors of sections Е, Б, В are in progress.

Building No.5
Installation of the pile field in section А is in progress.

Building No.6
Stripping is in progress

RC “Vidradnyi”

Building No.1
Installation of monolith frame – 100%    
Brickworks on external walls – 100%
Façade works – 97%
Plastering works – 100%
Screed – 100%
Decoration works in common use areas – 1st floor 95%
Decoration works – ground floor 95%
Roofing works are in progress – 90%  
Development of adjoining territory is in progress – 75%    
           
Building No.2 
Installation of monolith frame – 100%
Roofing works – 70%
Plastering works on the 7th floor are in progress.
Electric wiring and plumbing works on the 7th floor are in progress.
Installation of screed on the 6th floor is in progress.
Brickworks of external walls -95%. 
Filling of window openings – 90%
Brickworks on the ground floor are in progress

Building No.3
Reinforcing and concrete pour up to the 17th floor.
Brickworks on the 9th, 12th and 13th floors are in progress.
  
Building No.4:
Reinforcing of ceiling and floor slab on the 12th floor.
Brickworks on 5th, 6th, 7th and 8th floors are in progress.

Building No.5
Reinforcement and concrete pour of vertical structures on the 5th floor.

RC “Teremky”  

Stage 1– installation of vertical elements on 25th floor is completed.

Brickworks are completed 100% up to 20th floor inclusive, 21st floor is in progress.
Windows are installed up to 3d floor inclusive.

Stage 2 - installation of vertical elements on 5th floor is in progress.

Stage 3– installation of piles in section 4 is in progress.