PROGRESS OF CONSTRUCTION AS OF 13.09.18
PROGRESS OF CONSTRUCTION AS OF 13.09.18
13 september 2018

Progress of construction as of 13.09.18


RC "Volodymyrskyi"

Reinforcement and pouring of vertical structures on the 20th floor.
Brickworks at the basement and on 2, 4, 6, 8 floors are ongoing. Slab over the 19th floor has been completed. Commencement of works on installation of a formwork for the slab over the 20th floor. Brickworks for the basement , 2, 4, 6, 8, 9, 10, 11 floors are ongoing. Works on installation of concealed low-current wiring on typical residential floors inside monolith structures are in progress.
Plastering works – 5th floor
Finishing of GUP – 5th floor


RC “Syretski Sady”

Building No. 1
Completion of installation of windows and balconies – 95%.
Plumbing works -2-9 floors/Electric wiring works – 2-12 floors/
Plastering works – 4th to 6th floors.
Façade – heat insulation of walls has been commenced – 40%
Entrance groups – basements are completed
Finishing works have been commenced.


Building No. 2 
Brickworks – 1st to 12th floor.

Entrance groups – basements are completed

Roof – heat insulation has been completed.

Building No. 3 
Installation of vertical element of the 9th floor.

Building No.4
Installation of frame structures – 1-17th floor
Brickworks – 1st to 8th floor

Building No.5
Piles are being tested.

RC “Yaskravyi”

Building No.6 
Works on installation of walls, partitions, brickworks (external -90%, internal – 62%) are in progress. 
Installation of window structures-75%
Plumbing works –35%

Electric wiring works – 7%
Wall plastering – 7%
Installation of screed – 5%
Installation of elevators and adjustment – 70%
Roofing – 55%
Entrance group – 30%

Building No. 7 
Plumbing works – 86%
Electric wiring works – 77%
Ventilation and smoke exhaust system – 82%
Low-current systems – 84%
Finishing of GUP – 77%
Installation of elevators and adjustment – 81%
Façade works – 93%
Brickworks on the roof – 1%
Roofing – 97%.
Entrance group – 67%
Development of adjoining territory – 40%

RC “Parkovi Ozera” 

Building No. 12 
Decoration works inside apartments.

Building No. 13 
Installation of walls, partitions, brickworks (internal) - 95% (brickworks for parapets of entrance groups, intersection passes (15-25 floors to be completed), engineering accesses in the basement).

Installation of window structures - 96% (adjustment of handles, windowsills) 


Plumbing works – 35%
Electric wiring works – 26%
Ventilation and smoke exhaust system – 19%
Low-current systems – 17%
Wall plastering – 30% 
Installation of screed -26%

Installation of elevators and adjustment – 80%
Façade works – 37 %
Façade heat insulation 70%
Façade finishing – 44%
Roofing – 69%.
Entrance group – 42%

RC “Ozernyi Hai Gatne” 

Building No.2
Internal decoration -95%
Development of adjoining territory -98%

Building No. 3
Development of adjoining territory – 99%. 

Building No. 4
Internal decoration - 75%.

Building No. 5
Internal decoration - 70%.
Glazing – 95%
Façade – 92%

Building No.6
Monolith works : 1st floor – 68%

Installation and putting the tower cranes into operation– 96%.

RC “Traditsiya” 


Building No.2
Active finishing works inside apartments.

Building No.4

Vertical structure element of the 6th floor is in progress.

RC “Malakhit”


Building No.4
Section 401 – slab over the 21st floor. Brickworks on 10-18 floors.
Sections 403 – Plastering works – 2-8 floors. 
Sections 405-406 – finishing works are ongoing: Section 404 final decoration (tiling, painting) – 1-8 floors. Section 405 –final decoration –1st to 13th floors. Section 406 –final decoration –1st to 13th floors. Façade works – 65%
Works on waterproofing of parking areas are ongoing. Development of promenade zone – 35%.

RC “Nyvky-Park” 


Building No.3
Installation of window structures at the staircases of all sections is in progress.
Finishing works at GUP: section Ж – 16th floor, section Г - on the 6th floor and section Д on the 5th floor.

Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Roofing is in progress.
Installation of façade is in progress.

Building No.4

Works on installation of window structures: section Б – on the 17th floor and section В – on the 16th floor.
Plastering works at GUP: section Б – on the 17th floor and section B – on the 13th floor and section B – on the 14th floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Installation of screed – section Б – 15th floor, section B – on the 12th floor.
Installation of internal engineering systems is in progress: section B – on the 15th floor.
Installation of elevators is ongoing.
Finishing works and tiling at GUP: section Е – on the 12th floor, section Б – on the 8th floor, section В – on the 9th floor.


Building No.5
Installation of monolith frame
section A vertical element on the 17h floor, 
section E – slab over the 16th floor
section Б – vertical elements of the 16th floor.
Brickworks on the floors 1, 3, 4, 5, 6, 7 of section A; section Е - 
on the 1, 4, 5, 6, 7 floors and basement. Section Б -
on the 1, 2, 3, 4 and 6 floors.

Water proofing of basements at sections А, Б and Е.
Back filling of the pit is in progress.

Building No.6
Installation of the slab over the 7th floor at section Г
Installation of vertical elements of the 7th floor at section E.
Installation of vertical elements of the 7th floor at section Д*
Brickworks on the 2nd floor of section Г. 2nd floor of section Е and 2-3 floors of section Д *.

Building No.8
Excavation works on the pit are in progress.

RC “Vidradnyi” 

Building No.2 
Decoration works inside “turn-key” apartments ( 4, 5, 7, 8, 10, 11, 12 13, 16 floors).

Building No.3 
Roofing - 70%
Installation of metal and plastic windows - 95%.
Façades works are in progress  – 75%
Installation of cement and sand screed are in progress - 5, 8 floors.
Wall plastering on the 6th floors is in progress
Works on electric wiring and plumbing are in progress.
Works on installation of external mains are ongoing (K1, K2, BK).
Brickworks on the roof are ongoing.

Building No.4 


Installation of metal and plastic windows – 95%
Brickworks on the basement are in progress.
Façades works are in progress – 70%

Installation of external mains has been commenced.
Works on electric wiring and plumbing are in progress
Installation of cement and sand screed are in progress on the 6th floor is in progress.

Roofing is in progress.

Building No.5 
Brickworks on the floors 9, 12, 16 and basement are in progress.
Works on installation of metal and plastic windows are ongoing – 70%.

Façade works are in progress.- 10%

Installation of waterproof insulation on the basement – 50%.


RC “Teremky” 

1st stage.
Completion of installation of windows up to the 25th floor.
Heat insulation of the building is in progress. Roofing works are in progress. Painting of the façade is ongoing. 
Internal mains and plumbing works are in progress. Pouring of screed  - 13-15 floors.

Stage 2, section 2 – Brickworks on the 25th floor are ongoing. Installation of windows – on the 17th - 20th floors.
Stage 2, section 3 – slabs over the vertical elements on the 25th floor. Installation of windows on the 17th to 20th floors.
Stage 3, section 4. Slab over the vertical elements of the 15th floor is completed. Brickworks  - 2nd to 5th floors.
Stage 3, section 5 – Slab over the vertical elements of the 15th floor is in progress. Brickworks  - 5th floor.
Stage 3- section 6 – Slab over the vertical elements of the 14th floor is in progress.


Detailed photo reports of the construction progress are available on the websites of the complexes is sections “Gallery”.

Sincerely yours, Intergal-Bud Company