PROGRESS OF CONSTRUCTION AS OF 15.06.18
PROGRESS OF CONSTRUCTION AS OF 15.06.18
15 june 2018
Progress of construction as of 15.06.18

RC Volodymyrskyi

Completion of works for installation of frame structure - 5th to 11th floors. Works on the 12th floor have been commenced. Active brickworks – basement from 1st to 5th floors
Commencement of works for waterproofing, lightning protection system, internal electric supply networks, low-current networks and smoke exhaust system

RC “Syretski Sady”

Building No. 1
Works on the roofing are about to be completed. Installation of window structures – from 1st to 14th floors .

Building No. 2
Monolith elements are being poured.

Building No. 3
Installation of vertical structures on the 2nd floor.

Building No.4
Installation of vertical structures on the 10th floor is in progress.
Brickworks – 2 to 4 floors.

RC “Yaskravyi”

Building No.6
Active works on installation of walls, partitions, brickworks are in progress.
Plumbing and electric wiring works, installation of window structures and elevators are commenced,
Brickworks on the roof.

Building No. 7
Final stage of works for installation of walls, partitions, brickworks and window structures.
Active works on plumbing, electric wiring, installation of ventilation and smoke exhaust systems, wall plastering, arrangement of screed and installation of elevators and decoration of the general use premises, brickworks on the roof.
Works on arrangement of entrance group are commenced.

RC "Demiivka"

Plumbing works: – 1st to 20th floors.
Installation of heating radiators is being completed.
Screed: 18th to 20th floors, balconies.
Wall plastering: basement, IHSU, 1st to 20th floors.
Low-current systems – 1st to 20th floors and in basement.
Installation of window structures is completed – 1st to 12th floors. Installation of aprons is in progress

Active heat insulation, decorative layer and painting of balcony walls in apartments and main façade. Preparation works for water proofing. Installation of apartment entrance doors.
Active decoration works inside apartments.
Completion of works on electric wiring and heat supply networks.


RC “Parkovi Ozera”

Building No. 12
Completion of walls and partitions, wall plastering and installation of window structures
Active plumbing and electric wiring works are in progress.
Low-current systems, ventilation and smoke-exhaust systems, decoration of the general use premises, installation of elevators and entrance group are in progress.
Façade installation is in progress.

Building No. 13
Active installation of walls and partitions, brickworks,
window structures
In progress – low-current systems, wall plastering and screed, entrance group.



RC "Ozernyi Hai Gatne"

Building No.2
Completion of works for internal decoration and development of adjoining territory \


Building No. 3
Façade heat insulation and development of adjoining territory

Building No. 4
Completion of works on the roof and façade heat insulation.
Active internal decoration works and development of adjoining territory.


Building No. 5
Completion of works on installation of partitions and active glazing.


Building No.6
Ground excavation is completed

RC “Traditsiya”

Building No.2
Plastering works – 18th floor + apartments
Plumbing/ electric wiring – installation of water supply raises and electric boxes.
Puttying – 11th to 16th and 21st floors
Active works on the roof as well as heat insulation of façade and installation of elevators are in progress.
Tiling in corridors – 17th, 18th floors
Decoration works – 21st floor
Completion of façade heat insulation

RC “Malakhit”

Section 405-406 – brickworks – 13th floor
Section 401 vertical element of the 8th floor.
Sections 402-403 – works on installation of ventilation ducts are in progress.
Brickworks at sections 402-403 - works on the 8th floor are ongoing.
Installation of window structures: Section 404 – 406, - from 7th to 13th floor.
Decoration works at section 404 on the floors 7, 8 and 9.
Section 405 – on the floors from the 1st to 8th. Section 406 – from 1st to 3d floors.

RC “Nyvky-Park”

Building No.3
Brickworks for walls; works are completed except the locations where protruding platforms have been installed.
Installation of window structures is in progress at sections Д, on the 16th floor, section Ж – on 17th, and section Г – on the 16th and 17th floors.
Works on arrangement of internal mains are ongoing:
Section Г – the 5th floor, section Д – the 15th floor, section Ж – the 16th floor.
Decoration works at general use premises at sections Г on the 6th floor and section Д on the 12th floor are in progress.
Installation works for elevators in section Ж, Г and Д.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Roofing is in progress.
Installation of screed at sections Ж on the 14th floor and section Д on the 12th floor is ongoing.
Installation of doors: section Ж – on the 7th floor, section Д – on the 6th floor.
Arrangement of façade is ongoing.  

Building No.4
Brickworks for walls: works on section E are completed except the locations where protruding platforms have been installed. Works on the floors15 to 17 at section Б and B are ongoing.
Works on installation of window structures: section Е – on the 14th floor, section Б – on the 13th floor and section В – on the 11th floor.
Plastering works at general use premises: section Е – 7th floor, section Б  - on the 2d floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Decoration works inside general use premises on the 4th floor are ongoing.
Installation of screed.
Installation of internal engineering systems is in progress.
Installation of elevators is ongoing.

Building No.5
Installation of monolith frame
section A vertical structures of the 10th floor,
section E – vertical structures of the 9th floor
section Б – slab over the 7th floor.
Brickworks on the 2nd floor of sections A and Е.
Water proofing of basement  at sections А, Б and Е.


Building No.6
Installation of slab over the basement at section Г
Installation of vertical elements of the basement at section E.
Installation of vertical elements of the basement at section Д*

RC “Vidradnyi”

Building No.2
Water  proofing on the roof is ongoing
Electric wiring and installation of lighting devices on the floors 2-10 are in progress.
Completion of façade works.
Decoration works on the floors from basement up to 15th are ongoing.
Arrangement of entrances and pits of the basement.
Development of adjoining territory.  


Building No.3
Pouring of concrete structures is completed in full.
Brickworks are ongoing on the basement.
16th.
Active roofing works are ongoing.
Installation of window structures is completed.

Building No.4
Installation of window structures is ongoing.

Building No.5
Reinforcing of parapet on the 17th floor is in progress.
Brickworks on the floors from 5th to 13th.


RC “Teremky”

1st stage
Brickworks for vent ducts on the roof are ongoing.
Completion of installation of windows on 24th floor.
Installation of windows on the 25th floor is ongoing.
Commencement of works internal engineering and plumbing works of heat insulation works. Engineering and plumbing works are in progress.
Electric wiring works inside the building are in progress (floors 3, 4, 9, 11, 13).
Plastering of walls inside the turn-key apartments on the 13th floor is ongoing.
Pouring of floor screed on the 2nd, 3d and 5th floors.

Stage 2, section 2 – slab over the vertical elements on the 20th floor is in progress. Brickworks on the 10th and 16th floors are ongoing. Windows – 2nd to 8th floors
Stage 2, section 3 - slab over the vertical elements on the 20th floor is in progress. Brickworks on the 10th to 13th floors are ongoing.
Stage 3, section 4. Pouring of slabs over the vertical elements of the 7th floor is ongoing.
Stage 3- section 5 – Pouring of slabs over the vertical elements of the 6th floor is ongoing.
Stage 3- section 6 – Pouring of slabs over the vertical elements of the 2nd floor is in progress.