Progress of construction as of 16.08.18
Progress of construction as of 16.08.18
16 august 2018

Progress of construction as of 16.08.18

RC "Volodymyrskyi"

Installation of horizontal formwork for the slab over the 17 th floor.

Completion of brickworks at the basement and from 1-4 and 6-8 floors. Installation of external, internal walls and partitions.

Works for waterproofing, lightning protection system, internal electric supply networks, low-current networks and smoke exhaust system are ongoing.

Plastering of walls and finishing of common use premises area have been commenced.


RC “Syretski Sady” 

Building No. 1
Completion of installation of windows and balconies – from 9th to 16th floors.
Plumbing works -2-4 floors
Electric wiring works – 2-5 floors

Plastering works – 2nd floor.

Façade – heat insulation has been commenced

Entrance groups – basements are completed

Building No. 2 
Brickworks – 1st to 10th floor.

Building No. 3 
Installation of frame structures – 1st to 8th floor.

Building No.4
Installation of frame structures – 15th floor

Brickworks – 1st to 8th floor

Building No.5

Piles are being tested.

RC “Yaskravyi”

Building No.6 
Active works on installation of walls, partitions, brickworks on the roof are in progress. 
Active works on: plumbing and electric wiring works, installation of window structures and elevators, brickworks on the roof and entrance group.

Building No. 7 

Final stage of installation works on plumbing, electric wiring, installation of low-current systems, ventilation and smoke exhaust systems, finishing of the general use premises , installation of elevators and façade works, roofing and works at entrance group.

Brickworks on the roof, development of territory, installation of walls and partitions, brickworks have been commenced

RC “Parkovi Ozera” 

Building No. 12 
Ongoing repairs in apartments.

Building No. 13 
Completion of works on installation of walls and partitions, brickworks, window structures.

Active works on plumbing, electric wiring works and low-current systems, wall plastering, installation of screed and façade works.

Installation of ventilation and smoke-exhaust systems has been commenced.

RC “Ozernyi Hai Gatne” 

Building No.2
Completion of works for internal decoration and development of adjoining territory

Building
No. 3
Development of adjoining territory is being completed. 

Building No. 4
Active works on internal decoration.

Building No. 5
Completion of works on glazing.
Active façade works are in progress
Commencement of works on internal finishing.

Building No.6
Basement slab has been poured. Works on installation of reinforcement frame have been commenced.


RC “Traditsiya” 

Building No.2
Plumbing – works at IHSU are in progress.
Installation of elevators is being completed.

Active finishing works inside apartments and development of the territory are in progress.

Building No.4
Vertical structure element on the 4th floor, slab over the 3d floor. Backfilling is in progress.

RC “Malakhit”

Building No.4
Section 401 – slab over the 17th floor . Brickworks on 1-10 floors.
Sections 402-403 – installation of window structures is being completed.

Plastering works – 2-6 floors.
Sections 405-406 – finishing works are ongoing: Section 404 final decoration – 1-8 floors. Section 405 –final decoration –1st to 13th floors. Section 406 –final decoration –1st to 13th floors.

Works on waterproofing of parking areas П1-П4 are ongoing.


RC “Nyvky-Park” 

Building No.3
Installation of window structures at the general use premises in all sections is in progress.

Works on arrangement of internal mains are about to be completed in all sections.

Finishing works at GUP: section Г - on the 17th floor and section Д on the 15th floor.
Installation works for elevators: sections Ж, Г and Д.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.

Roofing is in progress.

Installation of doors: section Г – 8 th floor
Installation of façade.

Building No.4
Brickworks for walls: works on section E are completed except the locations where protruding platforms have been installed.

Works on installation of window structures: section Б – on the 14th floor and section В – on the 2nd floor.
Plastering works at GUP: section Е – on the 13th floor, section Б – on the 11th floor and section B – on the 11 floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Installation of screed – section Б – 13th floor, section B – on the 5th floor.

Installation of internal engineering systems is in progress: section Б – 14th floor, section B – on the 14th floor.
Installation of elevators is ongoing.

Building No.5
Installation of monolith frame
section A slab over the 14h floor, 
section E – vertical structures of the 14th floor
section Б – vertical structures of the 14th floor.
Brickworks on the floors 1, 3, 4 and 5 floors of sections A and on the 1, 4, 5, 6, 7 floors and basement of section Е. Section Б – on the 2, 3, 4 floors
Water proofing of basements at sections А, Б and Е.
Back filling of the pit is in progress.

Building No.6
Installation vertical elements of the 5th floor at section Г
Installation of the slab over the 4th floor at section E.
Installation of vertical elements of the 4th floor at section Д*

RC “Vidradnyi” 

Building No.2 
Decoration works inside “turn-key” apartments on the 4, 5, 6, 7 and 8 floors are ongoing.

Building No.3 
Completion of works on roofing and installation of metal and plastic windows.

Painting of façades is in progress.

Installation of cement and sand screed on the 2nd and 10th floors is in progress.

Wall plastering on the 2nd and 10th floors is in progress

Wall plastering on the basement is in progress.
Finishing works on the basement and heat insulation of walls in general use premises are ongoing.

Building No.4 

Completion of works on installation of metal and plastic windows.

Brickworks on the basement are in progress

Painting of facades is ongoing.

Installation of external mains has been commenced.

Building No.5 

Brickworks on the floors 9, 12, 14, 16 and basement are in progress.


RC “Teremky” 


1st stage.
Completion of installation of windows up to the 25th floor.
Heat insulation of the building is in progress. Roofing works are in progress. Plastering of façade is ongoing. Internal mains and plumbing works are in progress.
Electric wiring – 24th floor. Plastering works inside general use premises – 2nd to 23d floors.

Installation of windows on the 9th floor is in progress.

Stage 2, section 2 – Brickworks on the 19th to 23d floors are ongoing. Installation of windows – on the 9th floor.
Stage 2, section 3 – slabs over the vertical elements on the 25th floor.

Brickworks on the 16th to 17th floors are ongoing.

Stage 3, section 4. Slab over the vertical elements of the 12th floor is completed.
Stage 3- section 5 – Slab over the vertical elements of the 12th floor is completed. 
Stage 3- section 6 – Slab over the vertical elements of the 11th floor is in progress.

Detailed photo reports of the construction progress are available on the websites of the complexes is sections “Gallery”.

Sincerely yours, Intergal-Bud Company