PROGRESS OF CONSTRUCTION AS OF 18.05.18
PROGRESS OF CONSTRUCTION AS OF 18.05.18
18 may 2018
Progress of construction as of 18.05.18

RC Volodymyrskyi

Completion of works for installation of frame structure - 5th to 9th floors. Active works on the 10th floor.
Brickworks – basement from 1st to 4th floors
Commencement of works for waterproofing, lightning protection system, internal electric supply networks, low-current networks and smoke exhaust system

RC “Syretski Sady”

Building No. 1
Section 1: pouring of light bins.
Brickworks on the 12th, 13th, 14th  floors (internal walls)
Windows – 8th floor (w/o balconies)
Section 2: pouring of light bins.
Brickworks on the 10th, 11th, 12th, 13th, 14th, 15th floors and roof are in progress.
Windows – 8th floor (w/o balconies)

Building No. 2
Section 1: Reinforcing of floor slab over the 12th floor.
Brickworks – 2nd floor
Section 2: Reinforcing of floor slab over the 12th floor
Brickworks: - 2nd and 3d floors
Section 3: Installation of vertical structures on the 12th floor.
Brickworks – 1st floor.

Building No. 3
Installation of vertical structures on the basement.

Building No.4
Installation of vertical structures on the 8th floor is in progress.
Brickworks – 2nd floor.

RC “Yaskravyi”

Building No.6
Completion of works for monolith frame
Installation of walls, partitions, brickworks
Plumbing and electric wiring works are commenced,
Installation of window structures

Building No. 7
Completion of works for installation of walls, partitions, brickworks and window structures
Active works for plumbing, electric wiring, installation of ventilation and smoke exhaust systems, wall plastering, arrangement of screed and installation of elevators.
Decoration of the general use premises is commenced, façade works and roofing

RC "Demiivka"

Plumbing works: – 1st to 20th floors.
Installation of heating radiators is being completed.
Screed: basement, 1st to 17th floors, balconies.
Wall plastering: basement, IHSU, 1st to 20th floors.
Ventilation and smoke exhaust systems – installation of ventilation equipment on the roof and in basement has been completed;
Low-current systems – 1st to 20th floors and in basement.
Installation of elevators: No.1 and No.2.
Installation of window structures – 1st to 12th floors

Installation of heat insulation system for balcony walls in apartments and general facade.
Installation of doors: 2nd to 20th floors and in basement.
Decoration works inside apartments – laying of tiles and flooring at the premises of general use, basement and on floors 2th to 13th.
Completion of electric wiring and heat supply networks.

RC “Parkovi Ozera”

Building No. 12
Completion of walls and partitions, wall plastering and installation of window structures
Active plumbing and electric wiring works are in progress.
Low-current systems, ventilation and smoke-exhaust systems, decoration of the general use premises, installation of elevators are in progress.
Façade installation , screed on the roof are in progress.

Building No. 13
Installation of walls and partitions, brickworks
Installation of window structures – in progress
Plumbing and electric wiring works, wall plastering and screed have been commenced.



RC "Ozernyi Hai Gatne"

Building No.2
Completion of works for internal decoration and development of adjoining territory \


Building No. 3
Façade heat insulation and development of adjoining territory


Building No. 4
Completion of works on the roof and façade heat insulation.
Active internal decoration works and development of adjoining territory.


Building No. 5
Completion of works on installation of partitions and active glazing.


Building No.6
Ground excavation is completed

RC “Traditsiya”

Building No.2
Plastering works – floors 18, 19, 23 and 24
Plumbing/ electric wiring – pumping station and IHSU
Screed – 20th and 21th floors.
Puttying – 11th to 16th floors
Works on the roof, heat insulation of façade and installation of elevators are in progress.
Tiling in corridors – 14th floor
Decoration works – 8th floor

RC “Malakhit”

Building No. 4
Section 405-406 – brickworks – 13th floor
Section 401 vertical element of the 5th floor.
Sections 402-403 – works on installation of ventilation ducts are in progress.
Brickworks at sections 402-403 - works on the 6th floor are ongoing.
Installation of window structures: Section 404 – 406, - from 7th to 13th floor.
Decoration works at section 404 on the floors 7, 8 and 9.
Section 405 – on the floors 1, 2 and 3.

RC “Nyvky-Park”

Building No.1
Completion of works on development of adjoining territory (plant landscaping).
Installation of brackets for air-conditioners is in progress

Building No.2
Completion of works on development of adjoining territory (plant landscaping).
Installation of brackets for air-conditioners is in progress


Building No.3
Brickworks for walls; works are completed except the locations where protruding platforms have been installed.
Installation of window structures is in progress at sections Д, on the 12th floor, section Ж – on 14th, 15th and 16th floors and section Г – on the 13th and 14th floors.
Works on arrangement of internal mains are ongoing.
Decoration works at general use premises at sections Г and Д on 2nd to 14th floors are in progress
Installation works for elevators in section Ж, Г and Д.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Roofing is in progress.
Installation of screed at sections Г on the 7th  floor and section Д on the 5th floor is ongoing.

Building No.4
Brickworks for walls: works on section E are completed except the locations where protruding platforms have been installed. Works on the floors 11, 12, 13, 14 at section E, Б and B are ongoing.
Plastering works at general use premises.
Installation of external mains is in progress.
Installation of entrance groups is ongoing
Installation of internal engineering systems is in progress

Building No.5
Installation of monolith frame
section A vertical structures of the 6th floor,
section E – slab over the 6th floor
section Б – slab over the 4th floor.

Building No.6
Installation of vertical elements of the basement at section Г
Installation of vertical elements of the basement at section E.
Installation of vertical elements of the basement at section Д

RC “Vidradnyi”

Building No.2
Roofing works are ongoing
Plastering works on the 1st, 16th and basement floors are ongoing.
Electric wiring and plumbing works  on the 9th floor are in progress.
Filling of window openings on the basement.
Installation of screed on the 1st floor.
Completion of façade works.
Tiling works on the floors 5, 6, 7, 14 and 15.
Decoration works on floors 9, 10, 13 and 15 are ongoing.


Building No.3
Installation of vertical elements on the 18th floor.
Brickworks are ongoing on the 16th.
Roofing works are ongoing.

Building No.4
Completion of monolith frame .
Brickworks are ongoing on 16th floor.

Building No.5
Installation of floor slab over the 15th floor.
Brickworks on the floors from 3 to 10.

RC “Teremky”

1st stage
Brickworks for vent ducts on the roof are ongoing.
Completion of installation of windows on 22st and 23d floors.
Internal engineering and plumbing works are in progress. Electric wiring works inside the building are in progress (9th, 11th floors).
Plastering works inside the turn-key apartments on 9th and 11th floors are ongoing.
Pouring of floor screed on the 3d floor.

Stage 2, section 2 – brickworks on 9th and 11th floors are ongoing.
Stage 2, section 3 - slab over the vertical elements on the 17th floor is in progress. Brickworks on the 6th to 11th floors are ongoing.
Stage 3, section 4. Pouring of slabs over the vertical elements of the 6th floor is ongoing.
Stage 3- section 5 – Pouring of slabs over the vertical elements of the 4th floor is ongoing.
Stage 3- section 6 – reinforcement of the basement is in progress