Progress of construction as of 19.04.18
Progress of construction as of 19.04.18
19 april 2018

Progress of construction as of 19.04.18

RC “Volodymyrskyi”

Installation of frame structure for 5 floor up to +17,300 – 95%
Installation of frame structure for 6 floor up to +20,300 – 95%
Installation of frame structure for 7 floor up to +23,300 – 95%
Installation of frame structure for 8 floor up to +26,300 – 95%
Installation of frame structure for 9 floor up to +29,300 – 50%
Waterproofing – 0,5%
Installation of anti-lightning system - 0,8%
Installation of internal electric supply networks – 0,3%
Installation of internal low-current networks and smoke exhaust system – 0,3%
Brickworks for internal walls on the basement floor – 82%
Brickworks for external walls on the 1st floor – 90%
Brickworks for internal walls on the 1st floor – 10%
Brickworks for external walls on the 2nd floor – 80%
Brickworks for external walls on the 3d floor – 10,5%
Brickworks for external walls on the 4th floor – 86,72%
Brickworks for internal walls on the 4th floor – 65%


RC “Syretski Sady”

Building No. 1
Section 1: concrete structures of technical premises and on the roof.
Brickworks on the 8th to 10th floors are in progress.
Section 2: concrete pouring of the slab over the 16th floor is completed. Parapets on the roof are in progress.
Brickworks on the 10th and 11th floors are in progress.
Installation of window structures on the 3d floor has been commenced.

Building No. 2
Sections 1 and 2: vertical structures on the 9th floor are completed.
Section 3: floor and ceiling slab over the 8th floor is poured.
Brickworks on the 1st floor have been commenced [section2].

Building No. 3
Arrangement of concrete pad for basement slab is completed.

Building No.4
Installation of vertical structures on the 7th floor has been commenced.
Brickworks in the basement are completed.

RC “Yaskravyi”

Building No.6
Installation of monolith frame (2 cranes) – 96.3%
Installation of vent ducts – 68%
Installation of walls, partitions, brickworks (external) – 21%
Installation of walls, partitions, brickworks (internal) – 11.7%
Plumbing works – 12%
Installation of window structures – 3.6%
Electric wiring works – 1.3%

Building No. 7
Installation of walls, partitions, brickworks – 93%
Installation of window structures – 95%
Plumbing works – 56%
Electric wiring works – 44%
Ventilation and smoke exhaust systems – 51%
Low-current systems – 48%
Wall plastering – 57%
Arrangement of screed – 45%
Decoration of the general use premises – 18%
Installation of elevators and adjustment works – 45%
Façade works – 12%
Roofing – 35%

RC "Demiivka"

Plumbing works: installation of rises – 99%; installation of water and heat supply piping for the apartments on 1 to 20 floors – 99%; installation of basement networks, pumping station and IHSU -95%. Installation of heating radiators - 80%.
Electric wiring works are ongoing on 1 to 20 floors – 95%. Installation of networks in basement and IHSU is in progress.
Screed: basement – 99%; 1 to 12 floors – 99%; balconies – 90%. Works on 13th and 16th floors are ongoing.
Wall plastering: basement, 1-20 – 95%, IHSU – 95%
Ventilation and smoke exhaust systems – installation of ventilation equipment on the roof and in basement has been completed;
Low-current systems – 1-20 floors and in basement – 95%
Installation and adjustment works for elevators: installation of elevators No.1 and No.2.
Installation of window structures – 1-12 floors – 99%
Façade works – installation of heat insulation system for balcony walls in apartments and general facade.
Installation of doors (inclusive fire-proof doors) is completed at the cold passages from 2 to 20 floors and in basement – 80%. Installation of apartment entrance doors is ongoing.
Decoration works inside apartments – laying of tiles and flooring at the premises of general use, basement and on floors 2 to 10.
Engineering networks: electric wiring – 95%, heat supply – 95%


RC “Parkovi Ozera”

Building No. 12

Installation of walls and partitions – 99%
Installation of window structures – 95%
Plumbing works – 67%
Electric wiring works – 72%
Low-current systems – 65%
Ventilation and smoke-exhaust systems – 53%
Arrangement of screed – 62%
Wall plastering – 81%
Decoration of the general use premises – 22%
Façade installation – 40%
Installation of elevators – 52%
Roofing – 46%
Entrance group– 6%
Construction and assembling works – 37%

Building No. 13
Installation of walls and partitions, brickworks (external) – 54%
Installation of walls and partitions, brickworks (internal) – 37%
Installation of window structures – 34%
Plumbing works – 22%
Electric wiring works – 8%
Brickworks on the roof – 100%

RC "Ozernyi Hai Gatne"

Building No.2
Internal decoration – 92 %
Development of adjoining territory – 95 %

Building No. 3
Façade – 98%
Development of adjoining territory – 95 %

Building No. 4
Roof – 95 %
Façade – 90 %
Internal decoration - 85 %
Development of adjoining territory – 85%

Building No. 5
Plumbing works – 70%
Installation of partitions – 99%
Glazing – 85%

RC “Traditsiya”

Building No.2
Plastering works – 20th, 21st floors and on the roof
Plumbing/ electric wiring – 22-24 floors.
Screed – 11, 15 floors and basement
Puttying – 6th to 11th floors
Heat insulation of the basement is in progress – 90%
Roof – 60%
Façade - 10%
Elevators - 10%
Tiling in corridors – from 1st to 6th floor

RC “Malakhit”

Building No. 4
Section 405-406 – monolith frame -100%
Brickworks – 12th floor
Section 401 basement - 100 %, level - 3.100 – slab.
Works on the 1st floor are ongoing – 98%.
Sections 402-403 – works on the slab over the 8th floor are ongoing.
Brickworks at sections 402-403 level – 3.100 - 100% (works on the 3d floor are ongoing).
Sections 405-406 - Installation of window structures up to 5th floor inclusive.
Decoration works in section 404 on the floors 1-5 have been commenced.


RC “Nyvky-Park”

Building No.1
Installation of façade is completed by 99%
Decoration works inside the “turn-key” apartments are in progress.
Development of adjoining territory is in progress

Building No.2
Installation of façade is completed by 99%
Decoration works inside the “turn-key” apartments are in progress.

Building No.3
Brickworks for walls are ongoing: on the floors 14, 17 of sections Г, Д, Ж. Floors 15,16,17 and roof of section Д; 16th and 17th floors and roof in section Г;
Installation of window structures is in progress at sections Д, on the 11th floor, section Ж – on the 11th floor and section Г – on the 12th floor.
Works on arrangement of external networks are ongoing.
Decoration works on basement floor are in progress
Installation works for elevators in section Ж and Д.
Façade works on the balconies of section Ж on floors 2-10 are ongoing.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Roofing is in progress.
Decoration works in section Ж and 3d floor are in progress.

Building No.4
Brickworks for walls: works on 15, 16, 17th floors and roof in section E are ongoing.
Brickworks for walls: works on 10, 11, 12th floors and roof in section Б and B are ongoing.
Installation of window structures is in progress in sections Е, Б, В on the 6th and 7th floors.
Installation of external mains is in progress.
Installation of entrance groups is ongoing
Decoration works on the basement are in progress

Building No.5
Installation of monolith frame
section A slab over the 3d floor,
section E – vertical structures of the 3d floor
section Б – vertical structures of the 1st floor.

Building No.6
Reinforcing of the pile in section Г
Installation of pile field for section Е is ongoing.
Installation of basement for tower crane.

RC “Vidradnyi”

Building No.2
Roofing works are completed by 70%
Plastering works on the 17th and 18th floors are ongoing
Electric wiring and plumbing works are ongoing on the 16th floor are in progress
Brickworks for external walls – 95%
Filling of window openings – 90%
Installation of apartment entrance doors and those for technical premises is ongoing.
Tiling works on the 14th floor.
Decoration works on floors 4, 6, 10 and 14 are ongoing.

Building No.3
Installation of monolith frame is completed by 90%
Brickworks are ongoing on the 16th and 17th floors.

Building No.4
Reinforcing and pouring of vertical structures on the 17th floor.
Brickworks are ongoing on the floors 12, 14 and 15.

Building No.5
Reinforcing and pouring of the vertical elements of the 14th floor.
Brickworks on the floors 2, 3, 4, 5 and 6.

RC “Teremky”

1st stage
Brickworks are completed by 100% up to 25th floor inclusive.
Brickworks on the technical floor are about to be completed.
Monolith frame works are completed 100%.
Completion of installation of windows up to the 17h floor inclusive.
Internal engineering and plumbing works are in progress. Electric wiring works inside the building are in progress.
Stage 2, section 2 – slabs over the vertical elements on the 15th floor. Brickworks on the 7th floor are ongoing.
Stage 2, section 3 - slab over the vertical elements of the 14th floor is being poured. Brickworks on the floors to 7 are ongoing.
Stage 3 – section 4. Pouring of slabs over the vertical elements of the 3d floor is completed.
Stage 3- section 5 – Construction works on the basement floor are in progress.
Stage 3- section 6 – Installation of pile field -95%