PROGRESS OF CONSTRUCTION AS OF 19.07.18
PROGRESS OF CONSTRUCTION AS OF 19.07.18
19 july 2018
Progress of construction as of 03.07.18


RC "Volodymyrskyi"

Completion of works for installation of frame structure - 5th to 14th floors. Works on the 15th floor have been commenced.

Active brickworks – basement from 1st to 7th floors

Commencement of works for waterproofing, lightning protection system, internal electric supply networks, low-current networks and smoke exhaust system


RC “Syretski Sady”

Building No. 1


Works on the roofing are about to be completed.

Installation of balcony structures – from 12th to 14th floors .

Plumbing works are ongoing; Electric wiring works have been commenced.

Building No. 2

Brickworks – 7th floor.

Installation of window structures has been commenced


Building No. 3

Installation of vertical structures on the 7th floor.


Building No.4

Installation of vertical structures on the 15th floor is in progress.


Brickworks – floors 9-10.

Building No.5

Excavation is completed. Samples piles have been drilled.


RC “Yaskravyi”


Building No.6

Active works on installation of walls, partitions, brickworks are in progress.

Plumbing and electric wiring works, installation of window structures and elevators, brickworks on the roof and entrance group have been commenced,


Building No. 7

Final stage of brickworks at entrance groups, installation of window structures, wall plastering, arrangement of screed.

Active works on plumbing, electric wiring, installation of low-current systems, ventilation and smoke exhaust systems, installation of elevators and finishing of the general use premises, façade works and roofing.

Works on arrangement of entrance group and brickworks on the roof have been commenced.


RC "Demiivka"

Building No.2


Adjustment of hardware is conducted

Finishing works and installation of drains is about to be completed. Paint works on the floor of staircases.

Final stage of works on installation of lighting devices



RC “Parkovi Ozera”

Building No. 12
Completion of works on installation of window structures, plumbing, low-current and electric wiring works, ventilation and smoke-exhaust systems, installation of elevators, decoration of the general use premises, wall plastering, façade works and roofing
Entrance group and development of adjoining territory are in progress.


Building No. 13
Active installation of walls and partitions, brickworks,
window structures.

In progress – roofing works and entrance group.

Plumbing, electric wiring, low-current systems, wall plastering, installation of elevators are in progress.
Commenced: screed, façade thermal insulation.

RC "Ozernyi Hai Gatne"

Building No.2
Completion of works for internal decoration and development of adjoining territory \


Building No. 3
Façade heat insulation and development of adjoining territory


Building No. 4

Completion of works on façade heat insulation.


Building No. 5
Completion of works on glazing.

Insulation of façade has been commenced

Active works on internal decoration.

Building No.6
Excavation is completed
Works on arrangement of drainage system are ongoing

Preparation works for pouring of the basement are ongoing.

RC “Traditsiya”

Building No.2

Plastering works – inside apartments

Plumbing/ electric wiring – works at IHSU.

Puttying of GUP – 24th to 25th floors

Works on the roof as well as heat insulation of façade and installation of elevators are being completed.

Tiling in corridors – 25th floor

Active finishing works inside apartments and development of the territory are in progress.

Building No.4

Slab over the 1st floor. Vertical element of the 2nd floor. Water proofing and thermal insulation of the basement are in progress.

RC “Malakhit”

Building No.4

Section 401 – slab over the 12th floor

Sections 402-403 – installation of window structures – 4-5 floors. Plastering works – 2-3 floors. Roofing is in progress.

Sections 405-406 – finishing works are ongoing:
Section 404 – on 7,8 and 9 floors. Section 405 – from the 1st to 13th floor. Section 406 – from the 1st to 10th floors.

RC “Nyvky-Park”

Building No.3

Installation of window structures is in progress at section Д, on the 16th floor, section Ж – on the 16th and 17th floors.

Works on arrangement of internal mains are ongoing:
Section Г –7th floor, section Д –17th floor, section Ж –17th floor.

Decoration works at GUP in section Г are carried out on the 17th floor and section Д on the 14th floor.

Installation works for elevators in section Ж, Г and Д.

Installation of external mains is in progress.

Installation of entrance groups is ongoing.

Roofing is in progress.

Installation of screed at section Ж on the 17th floor and section Д on the 6th floor is ongoing.

Installation of doors: section Ж and Д – on the 11th floor.

Installation of façade is ongoing.

Building No.4

Brickworks for walls: works on section E are completed except the locations where protruding platforms have been installed. Works on the floors16 to 17 at section Б and B are ongoing.

Works on installation of window structures: section Е – on the 15th floor, section Б – on the 12th floor and section В – on the 11th floor.

Plastering works at GUP: section Е – on the 8th floor, section Б - on the 7th floor.

Installation of external mains is in progress.

Installation of entrance groups is ongoing.

Decoration works inside general use premises on the 8th floor are ongoing.

Installation of screed - section E – 16th floor, section Б – 7th floor.

Installation of internal engineering systems is in progress: section E – 15th floor, section Б – 7th floor.

Installation of elevators is ongoing.

Building No.5

Installation of monolith frame

section A vertical structures of the 13th floor,
section E – vertical structures of the 13th floor
section Б – slab over the 11th floor.

Brickworks on the floors 2, 3, 4 of sections A and 2, 3, 4 and 5 floors of section Е.

Water proofing of basements at sections А, Б and Е.

Building No.6

Installation of vertical elements of the first floor at section Г

Installation of vertical elements of the first floor at section E.

Installation of vertical elements of the basement at section Д*

RC “Vidradnyi”

Building No.2
Decoration works inside apartments are ongoing.

Building No.3
Completion of brickworks and installation of window structures.
Roofing, brickworks on the roof and façade installation are in progress.

Building No.4
Installation of windows, brickworks on the roof and façade installation are in progress.

Building No.5
Reinforcing of walls on the 18th floor is in progress.

Brickworks on the floors 3,11,14, 15 and 16.

RC “Teremky”

1st stage.

Completion of installation of windows up to the 25th floor.
Heat insulation of the building is in progress.
Plastering of façade is ongoing.

Internal mains and plumbing works are in progress.
Electric wiring inside the building on the 19th floor are in progress.

Stage 2, section 2 – Brickworks on the 16th to 19th floors are ongoing. Installation of windows – on the 9th floor.

Stage 2, section 3 - Brickworks on the 16th to 19th floors are ongoing. Installation of windows – on the 9th to 13th floors.

Stage 3, section 4. Slab over the vertical elements of the 9th floor is completed.

Stage 3- section 5 – Slab over the vertical elements of the 9th floor is completed.
Stage 3- section 6 – Slab over the vertical elements of the 7th floor is in progress.