PROGRESS OF CONSTRUCTION AS OF 20.09.18
PROGRESS OF CONSTRUCTION AS OF 20.09.18
20 september 2018
Progress of construction as of 20.09.18

RC "Volodymyrskyi"

Reinforcement and pouring of vertical structures on the 21st floor.
Pouring of the slab over the 20th floor is completed. Installation of the form work over the 20th floor has been commenced.
Brickworks at the basement and on 2, 4, 9, 10, 11, 12 floors are ongoing.
Works on installation of concealed low-current wiring on typical residential floors inside monolith structures are in progress.
Internal heating network and ventilation – 5th floor.
Internal water supply network and sewage – 5th floor.
Plastering works – 5th floor
Finishing of GUP – 5th floor

RC “Syretski Sady”

Building No. 1
Completion of installation of windows and balconies – 95%.
Plumbing works -2-11 floors/Electric wiring works – 2-12 floors
Plastering works – 4th to 7th floors.
Façade – heat insulation of walls is ongoing – 50%
Entrance groups – basements are completed
Finishing works – 50%.

Building No. 2
Brickworks – 1st to 12th floor.
Entrance groups – basements are completed
Roof – heat insulation is completed.


Building No. 3
Fr Installation of frame structures – 1-12 floors

Building No.4
Installation of frame structures – 1-17th floor
Brickworks – 1st to 8th floor

Building No.5
Piles are being tested - 30%

RC “Yaskravyi”

Building No.6
Works on installation of walls, partitions, brickworks (external -90%, internal – 63%) are in progress.
Installation of window structures-76%
Plumbing works –35.5%
Electric wiring works – 8%
Wall plastering – 8%
Installation of screed – 6%
Installation of elevators and adjustment – 70%
Roofing – 56.7%
Entrance group – 30%


Building No. 7
Plumbing works – 88%
Electric wiring works – 80%
Ventilation and smoke exhaust system – 85%
Low-current systems – 87%
Finishing of GUP – 82%
Installation of elevators and adjustment – 82%
Façade works – 97%
Brickworks on the roof – 1%
Roofing – 99%.
Entrance group – 98%
Development of adjoining territory – 60%


RC “Parkovi Ozera”

Building No. 12
Decoration works inside apartments.

Building No. 13
Installation of walls, partitions, brickworks (internal) - 96% (brickworks for parapets of entrance groups, intersection passes to be completed , engineering accesses in the basement).

Installation of window structures - 96% (adjustment of handles, windowsills)

Plumbing works – 35%
Electric wiring works – 30%
Ventilation and smoke exhaust system – 19%
Low-current systems – 17%
Wall plastering – 30%
Installation of screed -26%
Installation of elevators and adjustment – 80%
Façade works – 44 %
Façade heat insulation 74%
Façade finishing – 48%
Roofing – 69%.
Entrance group – 42%


RC “Ozernyi Hai Gatne”

Building No.2
Internal decoration -95%
Development of adjoining territory -98%

Building No. 3
Development of adjoining territory – 99%.

Building No. 4
Internal decoration - 80%.

Building No. 5
Internal decoration - 75%.
Glazing – 95%
Façade – 94%

Building No.6
Monolith works:
Section 1: 1st floor – 80%
Section 3: 2nd floor -30%



RC “Traditsiya”

Building No.2
Active finishing works inside apartments.


Building No.4
Vertical structure element of the 6th floor, slab over the 6th floor are in progress.

RC “Malakhit”

Building No.4
Section 401 – slab over the 22nd floor. Brickworks on 10-18 floors.
Sections 403 –  Plastering works – 2-8 floors.
Sections 405-406 – finishing works are ongoing: Section 404 final decoration (tiling, painting) – 1-8 floors. Section 405 –final decoration –1st to 13th floors. Section 406 –final decoration –1st to 13th floors. Façade works – 75%
Works on waterproofing of parking areas are ongoing. Development of promenade zone – 35%.


RC “Nyvky-Park”

Building No.3
Installation of window structures at the staircases of all sections is in progress.
Finishing works at GUP: section Ж are completed (except 1st floor),  section Г - on the 6th floor and section Д on the 7th floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Roofing is in progress: works in section Д.
Installation of façade is in progress.
Works on development of adjoining territory are in progress.



Building No.4

Works on installation of window structures: section B – on the 17th floor.
Plastering works at GUP: section E – up to the 17th floor and section Б – on the 14th floor and section B – on the 15th floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Installation of screed – section E – 17th floor, section B – on the 15th floor.
Finishing works and tiling at GUP: section Е – up to the 14h floor, section Б – on the 9th floor, section В – on the 9th floor.


Building No.5
Installation of monolith frame
section A slab over the 17h floor,
section E – slab over the 17th floor
section Б – vertical elements of the 17th floor.
Brickworks on the floors 1, 5, 6, 7, 8, 9 of section A; section Е -
on the 8, 9 floors and basement. Section Б - on the 1, 2, 3, 4, 5 and 6 floors.
Water proofing of basements at sections А, Б and Е.
Back filling of the pit is in progress.

Building No.6
Installation of the slab over the 8th floor at section Г
Installation of vertical elements of the 8th floor at section E.
Installation of the slab over the 7th floor at section Д*
Brickworks on the 3d floor of section Г. 2, 3, 4 floors of section Е and 2, 3, 4 floors of section Д *.

Building No.8
Excavation works on the pit are in progress. Arrangement of chip basis at section Г *.



RC “Vidradnyi”

Building No.2
Decoration works inside “turn-key” apartments (3,  4, 5, 7, 8, 10, 11, 12 13, 14, 15,16 floors).

Building No.3
Works on waterproofing on the roof are in progress.
Installation of metal and plastic windows - 95%.
Façades works are in progress  – 75% (works on the roof)
Installation of cement and sand screed are in progress - 15, 9 floors.
Wall plastering - on the 4, 5, 7 floors is in progress
Works on electric wiring and plumbing are in progress.
Works on installation of external mains are ongoing (gas supply line) .

Building No.4
Installation of metal and plastic windows – 95%
Brickworks on the roof are in progress.
Façades works are in progress – 70%
Installation of external mains (K1,K2,BK).
Works on electric wiring and plumbing are in progress.
Installation of cement and sand screed are in progress on the 4th floor is in progress.
Wall plastering – 2nd floor and basement
Roofing is in progress.

Building No.5
Brickworks on the floors 8, 16 and basement are in progress.
Works on installation of metal and plastic windows are ongoing – 70%.
Façade works are in progress.- 15%
Installation of waterproof insulation on the basement – 50%.


RC “Teremky”

1st stage.
Completion of installation of windows up to the 25th floor inclusive.
Heat insulation of the building is in progress. Roofing works are ongoing. Painting of the façade is ongoing.
Internal mains and plumbing works are in progress. Pouring of screed  - 15-16 floors.
Stage 2, section 2 – Brickworks on the 25th floor are ongoing. Installation of windows – on the 17th - 20th floors.
Stage 2, section 3 – slab over the vertical elements on the 25th floor is completed. Installation of windows on the 17th to 20th floors.
Stage 3, section 4. Slab over the vertical elements of the 16th floor is completed. Brickworks  - 2nd to 7th floors.
Stage 3, section 5 – Slab over the vertical elements of the 15th floor is in progress. Brickworks  - 5th to 6th floors.
Stage 3- section 6 – Slab over the vertical elements of the 15th floor is in progress.