Progress of construction as of 21.02.18
Progress of construction as of 21.02.18
21 february 2018
Progress of construction as of 21.02.18

RC “Volodymyrskyi”

Installation of frame structure for 5 floor up to +17,300 – 95%  
Installation of frame structure for 6 floor up to +20,300 – 95%
Installation of frame structure for 7 floor up to +23,300 – 95%
Installation of frame structure for 8 floor up to +26,300 – 10%
Waterproofing – 0,5%
Installation of anti-lightning system - 0,5%
Installation of internal electric supply networks – 0,15%
Installation of internal low-current networks and smoke exhaust system – 0,09%
Brickworks on the basement floor – 82%
Brickworks for external walls on the 1st floor – 90%
Brickworks for internal walls on the 1st floor – 10%
Brickworks for external walls on the 2nd floor – 80%
Brickworks for external walls on the 3d floor – 10,5%
Brickworks for external walls on the 4th floor – 86,72%
Brickworks for internal walls on the 4th floor – 65%

RC “Syretski Sady”

Building No.1
Section 1: concrete structures: completed for 13 floors.
Brickworks on the 6th floor are in progress.
Section 2: vertical structures on 12th floor are in progress.
Brickworks on the 5th floor are in progress.

Building No. 2
Section 1: vertical structures on 5th floor are in progress.
Section 2: vertical structures on 5th floor are in progress
Section 3: vertical structures on 4th floor are in progress

Building No. 3
Clearing of territory is completed.

Building No.4
vertical structures of the 4th floor and floor and ceiling slab over the 3d floor are in progress.

RC “Yaskravyi”  

Building No.6
Installation of monolith frame (2 cranes) – 81,5 %
Installation of vent ducts – 52,6 %
Installation of walls, partitions, brickworks – 3,3 %
Plumbing works – 3,3 %

Building No. 7  
Installation of walls, partitions, brickworks – 78%
Installation of window structures – 73%
Plumbing works – 48%
Electric wiring works – 38%
Ventilation and smoke exhaust systems – 44%
Low-current systems – 40%
Wall plastering – 30%
Arrangement of screed – 30%
Installation of elevators and adjustment works – 23%
Façade works – 3%
Roofing – 35%

RC "Demiivka"  

Plumbing works: installation of rises – 95%; installation of water and heat supply piping for the apartments on 2 to 20 floors – 95%; installation of basement networks, pumping station and IHSU.
Electric wiring works are ongoing on 2 to 20 floors – 95%
Screed: basement – 99%; 3 to 8 floors – 99%; balconies – 80%
Wall plastering works  – 95%
Ventilation and smoke exhaust systems –installation of the network in basement
Installation of window structures – 12-20 floors – 99%
Installation of doors (inclusive fireproof doors) is completed at the cold passages from 2 to 15 floor and in basement – 80% Installation of apartment entrance doors.
Installation and erection of elevators: delivery of equipment and installation of cargo elevator.
Low-current systems – 1-18 floors – 95%
Engineering networks: electric wiring – 90%, heat supply – 20%

RC “Parkovi Ozera”

Building No. 12
Installation of walls and partitions – 98%
Installation of window structures – 93%
Plumbing works – 56%
Electric wiring works – 46%
Low-current systems – 28%
Ventilation and smoke-exhaust systems – 30%
Arrangement of screed – 48%
Wall plastering – 63%
Decoration of general use premises – 16%
Installation of elevators – 21%
Roofing – 46%
Entrance – 6%
Construction and installation works – 37%

Building No. 13
Installation of monolith frame – 98%
Installation of walls and partitions, brickworks (external) – 34%
Installation of walls and partitions, brickworks (internal) – 29%
Installation of window structures – 5%
Plumbing works – 2%
Brickworks on the roof – 74%
  
RC "Ozernyi Hai Gatne"

Building No.2
Internal decoration – 90 %
Development of adjoining territory – 95 %

Building No. 3
Facade – 98%
Development of adjoining territory – 95 %

Building No. 4
Roof – 95 %
Facade – 85 %
Internal decoration - 75 %
Development of adjoining territory – 70%

Building No.5
Installation of ceilings – 95 % (10th floor)
Installation of monolith floor and ceiling slabs – 95 %
Installation of partitions – 90 %  

RC “Traditsiya”

Building No. 2
Brickworks are ongoing on 28th floor.
Installation of window structures on 22-24 floors.
Plastering works – 8-11 floors;
Plumbing/ electric wiring – 13-17 floors.
Arrangement of screed at the level of the 5th floor

RC “Malakhit”

Building No. 4
Installation of vertical reinforced concrete structures at sections 405-406 are ongoing – slab of the 11th floor.
Brickworks are ongoing from 3 to 7 floors.
Section 401 basement is completed by100 %,  level – 3.100
Section 402-403 – vertical element of the 8th floor.

RC “Nyvky-Park”

Building No.1
Installation of façade is completed by 99%

Building No.2
Installation of façade is completed by 96%
Erection and adjustment of elevators – regulation of stops.

Building No.3
Brickworks for walls are ongoing: on the floors 12, 13, 14,16 of sections Г, Д, Ж.
Installation of window structures is in progress at sections Д, Ж on the 6th floor, section Г - on 7,8,9,10 floors.

Building No.4:
Sections Е, В installation of floor and ceiling slabs over the elevator machine premises are in progress.
Section В – installation of monolith parapet.
Brickwork of walls: works on the 8,9,10,11 floors of sections Е, Б, В.
Installation of window structures is in progress at sections Е, Б, В on 4,5 floors.

Building No.5
Installation of the pile field for sectio Е is being completed.
Installation of vertical elements of the basement at section А is in progress

Building No.6:
Installation of test piles is ongoing.

RC “Vidradnyi”

Building No.2  
Roofing is completed for 70%
Plastering works on the 11th floor are ongoing .  
Electric wiring and plumbing works are ongoing on the 11th floor.
Brickworks for external walls are completed by 95%
Filling of window openings is completed by 90%
Brickworks on the basement are completed by 90%
Installation of doors for technical premises and apartment entrance doors are ongoing.

Building No.3
Installation of monolith frame is completed by 90%
Brickworks are ongoing on 12, 15, 16  floors.

Building No.4
Reinforcing and pouring of vertical structures on the 16th floor.
Brickworks are ongoing on 1, 6, 7, 9, 10, 11, 12, 13 floors.

Building No.5
Reinforcing and pouring of the slab over the 8th floor.

RC “Teremky”

I stage

Brickworks are completed by 100% on 24th floor. 25th floor is currently being completed.
Installation of window structures is being completed on 10the floor. Preparation for installation of windows on 11and 12 floors is ongoing.
2 stage, 2 section – slab over the 9th floor is completed. Installation of slab over the vertical elements on the 10th floor is ongoing.
2 stage, 3 section - slab over the 9th floor is completed. Installation of slab over the vertical elements on the 10th floor is ongoing.
3 stage – pile field at section 4 is installed. Preparation for installation of basement is ongoing