Progress of construction as of 22.03.18
Progress of construction as of 22.03.18
22 march 2018
Progress of construction as of 22.03.18

RC “Volodymyrskyi

Installation of frame structure for 5 floor up to +17,300 – 95%
Installation of frame structure for 6 floor up to +20,300 – 95%
Installation of frame structure for 7 floor up to +23,300 – 95%
Installation of frame structure for 8 floor up to +26,300 – 95%
Waterproofing – 0,5%
Installation of anti-lightning system - 0,6%
Installation of internal electric supply networks – 0,15%
Installation of internal low-current networks and smoke exhaust system – 0,09%
Brickworks on the basement floor – 82%
Brickworks for external walls on the 1st floor – 90%
Brickworks for internal walls on the 1st floor – 10%
Brickworks for external walls on the 2nd floor – 80%
Brickworks for external walls on the 3d floor – 10,5%
Brickworks for external walls on the 4th floor – 86,72%
Brickworks for internal walls on the 4th floor – 65%
Installation of internal electric supply networks – 0,2 %
Installation of internal low-current networks and smoke exhaust


RC “Syretski Sady”

Building No. 1
Section 1: concrete structures of technical premises on the roof.

Brickworks on the 9th floor are in progress.
Section 2: concrete pouring of the slab over the 15th floor is completed.
Brickworks on the 9th floor are in progress.

Building No. 2

Section 1: concrete pouring of vertical structures on the 7th floor is ongoing.
Section 2: concrete pouring of vertical structures on the 7th floor is ongoing.
Section 3: reinforcing of the slab over the 5th floor is in progress.
Brickworks in the basement have been commenced.

Building No. 3
Excavating works in the pit are completed.

Building No.4
reinforcing and pouring of the vertical structures on the 6th floor is ongoing.
Brickworks in the basement have been commenced.


RC “Yaskravyi”

Building No.6

Installation of monolith frame (2 cranes) – 95.2%
Installation of vent ducts – 68%
Installation of walls, partitions, brickworks (external) – 4.8%
Installation of walls, partitions, brickworks (internal) – 6.5%
Plumbing works – 7.2%


Building No. 7

Installation of walls, partitions, brickworks – 85%
Installation of window structures – 81%
Plumbing works – 53%
Electric wiring works – 41%
Ventilation and smoke exhaust systems – 48%
Low-current systems – 44%
Wall plastering – 40%
Arrangement of screed – 34%
Decoration of the general use premises – 14 %
Installation of elevators and adjustment works – 35%
Façade works – 4%
Roofing – 35%

RC "Demiivka"

Plumbing works: installation of rises – 99%; installation of water and heat supply piping for the apartments on 1 to 20 floors – 99%; installation of basement networks, pumping station and IHSU -90%. Installation of heating radiators - 60%.
Electric wiring works are ongoing on 1 to 20 floors – 95%. Installation of networks in basement and IHSU is in progress.
Screed: basement – 99%; 3 to 9 floors – 99%; balconies – 80%. Works on 11th floor are ongoing.
Wall plastering: 1,3,4-13 floors – 95%, 2,14, 15, 16, 18, IHSU – 95%
Ventilation and smoke exhaust systems – installation of ventilation equipment on the roof has been completed; installation of networks in basement is in progress.
Low-current systems – 1-20 floors and in basement – 95%
Installation and erection of elevators: delivery of equipment and installation of elevators No.1 and No.2.
Installation of window structures – 1-12 floors – 99%
Façade works – installation of heat insulation system for balcony walls in apartments.
Installation of doors (inclusive fire-proof) is completed at the cold passages from 2 to 15 floor and in basement – 80%.
Installation of apartment entrance doors is in progress.
Roofing is completed: heat insulation – 100%, sloping layer – 100%, screed -100%.
Decoration works inside apartments – laying of tiles at the general use premises, basement and on floors 3, 4 and 6.
Engineering networks: electric wiring – 90%, heat supply – 20%

RC “Parkovi Ozera”

Building No. 12

Installation of walls and partitions – 99%
Installation of window structures – 95%
Plumbing works – 59%
Electric wiring works – 48%
Low-current systems – 33%
Ventilation and smoke-exhaust systems – 30%
Arrangement of screed – 53%
Wall plastering – 67%
Decoration of general use premises – 20%
Installation of elevators – 33%
Roofing – 46%
Entrance group– 6%
Construction and assembling works – 37%

Building No. 13

Installation of monolith concrete frame – 99%
Installation of walls and partitions, brickworks (external) – 44%
Installation of walls and partitions, brickworks (internal) – 31%
Installation of window structures – 16%
Plumbing works – 6%
Electric wiring works – 4%
Brickworks on the roof – 77%

RC "Ozernyi Hai Gatne"

Building No.2

Roof – 95%
Facade – 95 %
Internal decoration – 90 %
Development of adjoining territory – 95 %

Building No. 3

Roof – 95 %
Façade – 98%
Development of adjoining territory – 95 %

Building No. 4

Roof – 90 %
Façade – 90 %
Internal decoration - 81 %
Development of adjoining territory – 70 %

Building No. 5

Roof – 99%
Installation of partitions – 96 %

RC “Traditsiya”

Brickworks are completed.
Installation of window structures on 25th floor;
Plastering – 17th floor;
Plumbing/ electric wiring – 18-19 floors.
Plastering works – 2-3 floors
Heat insulation of the basement is in progress

RC “Malakhit”

Building No. 4

Installation of vertical reinforced concrete structures at sections 405-406 are ongoing – slab over the 12th floor.
Brickworks are ongoing from 3 to 9 floors.
Section 401 basement is completed by100 %, level – 3.100 (vertical element) – 100%
Works on the basement are completed.
Sections 402-403 – vertical element of the 8th floor.
Brickworks at sections 402-403 level – 3.100 - 100% (works on the ground floor have been commenced).
Installation of window structures (section 404) – 80%
Decoration works in section 404 are ongoing.

RC “Nyvky-Park”

Building No.1

Installation of façade is completed by 99%

Building No.2

Installation of façade is completed by 96%
Erection and adjustment of elevators – regulation of stops.

Building No.3

Brickworks for walls are ongoing: on the floors 12, 13, 14, 16 of sections Г, Д, Ж.
Installation of window structures is in progress at sections Д, on the 10th floor, section Ж – on the 11th floor and section Г – on the 12th floor.

Brickworks for ventilation ducts are ongoing on the roof of section Ж.
Works on arrangement of external networks are ongoing.

Building No.4:
.
Section В – installation of monolith parapet.
Brickwork of walls: works on the 10,11,14, 15 floors of section Е.
Brickwork of walls: works on the 10th floor of section Б, В.
Installation of window structures is in progress at sections Е, Б, В on the 4th and 5th floors.

Building No.5

Works on installation of vertical elements of the ground floor at section A are in progress.
Works on installation of vertical elements of the basement at section E are in progress
Works on installation of the slab at the level 0.100 at section E have been commenced.
Works on installation of vertical elements of the basement at section Б are in progress

Building No.6

Excavating works are ongoing

RC “Vidradnyi”

Building No.2

Roofing is completed for 70%
Plastering works on the 13th and 14th floors are ongoing
Electric wiring and plumbing works are ongoing on the 15th floor are in progress
Brickworks for external walls – 95%
Filling of window openings – 90%
Brickworks on the basement – 90%
Installation of apartment entrance doors and those on the 6th floor is ongoing.

Building No.3

Installation of monolith frame - 90%
Brickworks are ongoing on the 16th floor.
Installation of windows – 10th floor

Building No.4

Reinforcing and pouring of vertical structures on technical floor.
Brickworks are ongoing on 1, 6, 7, 9, 10, 11, 12 and 13 floors.


Building No.5
Reinforcing and pouring of the slab over the 10th floor.
Brickworks for the walls on the 2nd floor.

RC “Teremky”

1st stage
Brickworks are completed by 100% up to 24th floor. 25th floor is currently being completed.
Installation of window structures up to the 11th floor is completed. Installation of windows is about to be completed on the 15th and 16th floors.
Stage 2, section 2 – slab over the vertical elements on the 12th floor. Brickworks from the 2nd and up to 5th floor are ongoing.
Stage 2, section 3 - slab over the vertical elements of the 11th floor is completed. Brickworks on the floors 2, 3 and 4 are ongoing.
Stage 3 – section 4. Pile field is completed. Monolith works on the ground floor are in progress.
Stage 3- section 5 – Pile field is completed. Installation of reinforcing elements on the basement is ongoing.
Stage 3- section 5 – Installation of pile field is in progress