Progress of construction as of 23.08.18
Progress of construction as of 23.08.18
23 august 2018
Progress of construction as of 23.08.18

RC "Volodymyrskyi"

Installation of vertical structures of the 18th floor.
Brickworks at the basement and from 2, 4, 6, 8 floors are ongoing. Installation of external, internal walls and partitions.
Works for waterproofing, lightning protection system, internal electric supply networks, low-current networks and smoke exhaust system are ongoing.
Plastering of walls and finishing of common use premises area and installation of external mains have been commenced.

RC “Syretski Sady”

Building No. 1
Completion of installation of windows and balconies – 90%.
Plumbing works -2-5 floors/Electric wiring works – 2-10 floors/
Plastering works – 3d floor.
Façade – heat insulation has been commenced
Entrance groups – basements are completed

Building No. 2
Brickworks – 1st to 12th floor.

Building No. 3
Installation of frame structures – 1st to 9th floor.

Building No.4
Installation of frame structures – 1-15th floor
Brickworks – 1st to 8th floor

Building No.5
Piles are being tested.

RC “Yaskravyi”

Building No.6
Works on installation of walls, partitions, brickworks (external -79.8%, internal – 56.5%) are in progress.
Brickworks on the roof – 43.9%
Installation of window structures-43,9%
Plumbing works – 24,9%
Wall plastering – 0,5%
Installation of screed – 1,1%
Installation of elevators and adjustment – 70%
Roofing – 33,3%
Entrance group – 8,3%

Building No. 7
Plumbing works – 81%
Electric wiring works – 73%
Ventilation and smoke exhaust system – 78%
Low-current systems – 78%
Finishing of GUP – 70%
Installation of elevators and adjustment – 80%
Façade works – 85%
Brickworks on the roof – 1%
Roofing – covering of parapets, water drain pipes.
Entrance group – 60%
Development of adjoining territory – 15%

RC “Parkovi Ozera”

Building No. 12
Decoration works inside apartments.
Building No. 13
Installation of walls, partitions, brickworks (internal) - 93% (engineering recesses on 21st and 24th floors, intersection passes, engineering accesses in the basement).
Installation of window structures - 89% (adjustment of handles, windowsills)
Plumbing works – 33% (4-14 floors)
Electric wiring works – 22% (1-15 floors)
Ventilation and smoke exhaust system – 11%
Low-current systems – 17%(4-13 floors)
Wall plastering – 26%
Installation of screed -21% (7, 13, 25 floors (cold passages)
Installation of elevators and adjustment – 80%
Façade works – 24%
Façade heat insulation 44%
Façade finishing – 25%
Roofing – 69%.
Entrance group – 60%

RC “Ozernyi Hai Gatne”

Building No.2
Internal decoration -72%
Development of adjoining territory -98%

Building No. 3
Development of adjoining territory – 99%.

Building No. 4
Internal decoration - 70%.

Building No. 5
Internal decoration - 50%.
Glazing – 92%
Façade – 76%

Building No.6
Pouring of basement slab.
Frame – 16%
Installation and putting into operation of tower cranes – 90%.

RC “Traditsiya”

Building No.2
Plumbing – works at IHSU are in progress.
Active finishing works inside apartments and development of the territory are in progress.

Building No.4
Vertical structure element on the 4th floor, slab over the 4th floor. Backfilling is in progress.

RC “Malakhit”

Building No.4
Section 401 – slab over the 18th floor . Brickworks on 1-10 floors.
Sections 402-403 – installation of window structures is being completed. Plastering works – 2-6 floors.
Sections 405-406 – finishing works are ongoing: Section 404 final decoration – 1-8 floors. Section 405 –final decoration –1st to 13th floors. Section 406 –final decoration –1st to 13th floors.
Works on waterproofing of parking areas П1-П4 are ongoing.

RC “Nyvky-Park”

Building No.3
Installation of window structures at the general use premises in all sections is in progress.
Finishing works at GUP: section Г - on the 17th floor and section Д on the 15th floor. Finishing works at GUP at section Ж are ongoing.
Installation works for elevators: sections Ж, Г and Д.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Roofing is in progress.
Installation of doors: section Г – 11th floor
Installation of façade.

Building No.4
Brickworks for walls: works on sections are completed except the locations where protruding platforms have been installed.
Works on installation of window structures: section Б – on the 15th floor and section В – on the 14th floor.
Plastering works at GUP: section Е – on the 13th floor, section Б – on the 12th floor and section B – on the 11th floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Installation of screed – section Б – 13th floor, section B – on the 8th floor.
Installation of internal engineering systems is in progress: section Б – 14th floor, section B – on the 14th floor.
Installation of elevators is ongoing.
Finishing works and tiling at GUP: section Е – 9th floor, section Б – 5th floor, section В – 6th floor.


Building No.5
Installation of monolith frame
section A vertical elements of the 15h floor,
section E – slab over the 14th floor
section Б – slab over the 14th floor.
Brickworks on the floors 1, 3, 4, 5 and 6 of sections A;
on the 1, 4, 5, 6, 7 floors and basement of section Е.
on the 2, 3, 4 and 6 floors of Section Б
Water proofing of basements at sections А, Б and Е.
Back filling of the pit is in progress.

Building No.6
Installation of the slab over the 5th floor at section Г
Installation of vertical elements of the 5th floor at section E.
Installation of vertical elements of the 5th floor at section Д*
Brickworks on the 2nd floor of section Г.

Building No.8
Excavation works on the pit are in progress.

RC “Vidradnyi”

Building No.2
Decoration works inside “turn-key” apartments ( 4, 5, 6, 7 8 and 14 floors).

Building No.3
Roofing - 70%
Installation of metal and plastic windows - 95%.
Façades works are in progress (painting).
Installation of cement and sand screed are in progress - 4, 12 floors.
Wall plastering on the 2nd and 10th floors is in progress
Wall plastering works on the basement is in progress.
Works on electric wiring and plumbing are in progress.
Works on installation of external mains are ongoing (К1,К2,ВК)

Building No.4

Installation of metal and plastic windows – 95%
Brickworks on the basement are in progress.
Façades works are in progress (painting).
Installation of external mains has been commenced.
Works on electric wiring and plumbing are in progress

Building No.5
Brickworks on the floors 9, 10, 12, 13 and basement are in progress.
Works on installation of metal and plastic windows are ongoing

RC “Teremky”

1st stage.
Completion of installation of windows up to the 25th floor.
Heat insulation of the building is in progress. Roofing works are in progress. Plastering of façade is ongoing.
Internal mains and plumbing works are in progress.
Electric wiring – 24th floor. Plastering works -24th floor (inside general use premises –25th floor).
Stage 2, section 2 – Brickworks on the 22nd to 25th floors are ongoing. Installation of windows – on the 14th floor.
Stage 2, section 3 – slabs over the vertical elements on the 25th floor.
Brickworks on the 21st to 24th floors are ongoing. Installation of windows on the 17th floor
Stage 3, section 4. Slab over the vertical elements of the 13th floor is completed.
Stage 3, section 5 – Slab over the vertical elements of the 13th floor is in progress.
Stage 3- section 6 – Slab over the vertical elements of the 12th floor is in progress.

Detailed photo reports of the construction progress are available on the websites of the complexes is sections “Gallery”.

Sincerely yours, Intergal-Bud Company