Progress of construction as of 24.01.18
Progress of construction as of 24.01.18
24 january 2018
Progress of construction as of 24.01.18

RC “Volodymyrskyi”

Installation of frame of the 5th floor at the level +17.300 – 95%  
Installation of frame of the 6th floor at the level +20.300 – 75% 
Installation of frame of the 6th floor at the level +23.300 – 20% 
Waterproofing – 0.5% 
Installation of lightning protection system - (0.07%) 
Internal electric wiring network – commenced (0.08%) 
Installation of internal low-current networks and fume exhaust system -0.07%
Brickwork at the ground floor – 82% 
Brickwork at the first floor – 40% 
Brickwork at the second floor – 47% 
Brickwork at the third floor – 5.5% 
Brickwork at the fourth floor – 28%   

RC “Syretski Sady”   

Building No. 1 
Section 1: concrete slab on the 10th floor has been poured
Works on the 11th floor are in progress; 
Brickworks on 2nd and 3d floors have been commenced 
Waterproofing – 85% 
Section 2: Works on the 9th floor are in progress Brickworks on 1st and 2nd floors have been commenced 
Waterproofing 85% 

Building No. 2 

Section 1: works over the 2st floor are in progress; 
Section 2: works on the 2st floor are in progress; 
Section 3: slab over the 1st floor is completed. 

Building No. 3 

Clearing of the territory is completed. 

Building No.  4 
Vertical structures of the 1st floor are completed   

RC “Yaskravyi”  

Building No.6 
  

Installation of the monolith frame (while installing 2 cranes) – 75.9% 
Installation of ventilation ducts – 44.9% 

Building No. 7 

Installation of walls, partitions, brickwork – 67% 
Installation of window structures – 63% 
Plumbing works– 45% 
Electric installation works – 34% 
Ventilation and smoke exhaust systems – 36% 
Low-current system – 35% 
Wall plastering – 26% 
Screed – 27% 
Installation of elevators and erection works – 8% 
Brickwork on the roof – 100% 
Roofing – 35%   

RC “Ozernyi Hai Gatne”   

Building No. 2 

Roofing – 95%
Façade – 95 %
Internal finishing works – 87 %
Development of the adjoining territory – 95 %

Building No. 3

Roofing – 98 %
Façade  – 98%
Development of the adjoining territory – 88 %

Building No. 4

Roofing – 75%
Façade  – 80 % 
Internal finishing works - 65 %
Development of the adjoining territory – 60 %

Building No. 5

Installation of ceilings – 92 % (9th floor). 
Installation of monolith ceiling and floor slab– 90 %
Installation of partitions – 85 %   

RC “Demiivka”  

Plumbing works: Installation of water supply rises, heating and domestic sewage pipes is ongoing from 2nd to 20th floor – 95%
Installation of basement networks is in progress.
Electric wiring works are ongoing from 2nd to 20th floor -90%
Floor screed: basement -99%, 3d to 8th floor – 99%, balconies – 80%. 
Wall plastering – 95% 
Ventilation and fume exhaust systems is completed on the roof.
Installation of windows at 19th -20th floors is ongoing – 85% 
Installation of doors (incl. fire-proof doors) is completed at cold passages from 2nd to 15th floors and basement -80%
Installation and erection of elevators – delivery of equipment and installation of cargo elevator are ongoing.
Low-current systems – 2-15 floors – 95% 
Roofing – 100% 
Engineering networks: wiring – 90%, heating – 20%   

RC "Parkovi Ozera"  

Building No.11 

Plumbing works – 89%
Installation of the system of internal mains – 95%
Low-current systems – installation of electric meters are being completed -96 %
Ventilation and smoke exhausting – 97 %
Installation of elevators – 93 % 
Engineering networks – 96% 
Putting into operation – 99%

Building No.12

Installation of walls and partitions – 90%
Installation of window structures – 70%
Plumbing works – 51%
Electric wiring works – 37%
Low-current systems – 26% 
Ventilation and fume exhaust systems – 30% 
Arrangement of screed – 38%
Wall plastering – 53%
Decoration of the common use areas – 16% 
Installation of elevators – 11%
Roofing – 46%
Entrance group – 6%
Construction works – 30%

Building No. 13 

Installation of monolith frame – 96%
Installation of walls and partitions – 14%

RC “Traditsiya” 

Brickworks are in progress on 26-28 floors
Installation of window structures on15-17 floors.
Plastering works on the 8th floor.
Plumbing/ electric works – 6-8 floors.
Screed at the level of the 2nd floor.  
  
RC “Malakhit”  

Installation of vertical reinforced concrete structures are in progress in sections 405-406 – 7th floor.
Brickwork on floors 3 to 4. 
Section 401 basement - 100 %, level – 3.100
Section 402-403 –vertical element of the third floor.   

RC “Nyvky-Park” 

Building No.1

Installation of façade is completed by 99%.
Start-up and adjustment works for elevators are in progress 
Arrangement of entrance groups is in progress
Works on development of the court yard are in progress.

Building No.2

Installation of façade is completed by 95%.
Start-up and adjustment works for elevators are in progress 
Arrangement of entrance groups is in progress
Works on development of the court yard are in progress.

Building No.3

Sections Г, Д, Ж: works on installation of monolith slabs over the machine premises of elevators are in progress.
Brickworks of walls: works on 10-12 floors, sections Г, Д, Ж are in progress.
Commenced to installation of window structures on sections Г, Д, Ж on the 4th floor.

Building No.4

Sections Е, Б, В works on installation of monolith frame of the 17th floor are in progress.
Brickworks of walls: works on 6-9 floors of sections Е, Б, В are in progress.

Building No.5

Installation of the pile field in section B is in progress.
Basement slab for section A is completed.

Building No.6 

Stripping is in progress 

RC “Vidradnyi” 
            
Building No.2 

Roofing works are completed by 70% 
Plastering works on the 8th floor are in progress.
Electric wiring and plumbing works on the 9th floor are in progress. 
Brickworks for external walls are completed by 95%.  
Filling of window openings – 90% 
Brickworks on the ground floor are in progress 
Installation of doors in technical premises has been commenced.

Building No.3 

Arrangement of monolith frame is completed by 90%
Brickworks on the 9th and 13th floors are in progress.
  
Building No.4

Reinforcing of ceiling and floor slab on the 14th floor. 
Brickworks on the 6th, 7th, 8th and 10th floors are in progress. 

Building No.5 

Reinforcement and concrete pour of the slab over the 6th floor. 

RC “Teremky”   

Stage 1– installation of the slab over the technical floor is ongoing.
Brickworks are completed 100% up to 20th floor inclusive, 21st and 23th floors are in progress. 
Windows are installed up to 6th floor inclusive.
Stage 2, section 2 - installation of vertical elements on 7th floor is in progress.
Stage 2, section 3 - installation of the slab on the 6th floor is in progress
Stage 3– installation of piles in section 4 is in progress.