PROGRESS OF CONSTRUCTION AS OF 27.09.18
PROGRESS OF CONSTRUCTION AS OF 27.09.18
27 september 2018
Progress of construction as of 27.09.18

RC "Volodymyrskyi"

Pouring of vertical structures on the 21st floor is completed.
Pouring of the horizontal formwork for the slab over the 21st floor has been commenced.
Brickworks at the basement and on 2, 4, 9, 10, 11, 12 floors are ongoing.
Works on installation of concealed low-current wiring on typical residential floors inside monolith structures are in progress.
Internal heating network and ventilation – 5th floor.
Internal water supply network and sewage – 5th floor.
Plastering works – 5th floor
Finishing of GUP – 5th floor

RC “Syretski Sady”

Building No. 1
Completion of installation of windows and balconies – 95%.
Plumbing works -2-14 floors/Electric wiring works – 2-12 floors/
Plastering works – 4th to 8th floors.
Façade – heat insulation of walls is ongoing – 50%. Works on decorative finishing have been commenced.
Entrance groups – basements are completed
Finishing works – 70% (2nd floor).

Building No. 2
Brickworks – 1st to 12th floor.
Entrance groups – basements are completed
Roof – heat insulation and screed are completed.


Building No. 3
Installation of frame structures – 1-12 floors

Building No.4
Installation of frame structures – 1-17th floor
Brickworks – 1st to 9th floor.

Building No.5
Piles are being tested - 80%

RC “Yaskravyi”

Building No.6
Works on installation of walls, partitions, brickworks (external -90%, internal – 71.7%) are in progress.
Installation of window structures-76%
Plumbing works –35.5%
Electric wiring works – 9%
Wall plastering – 8%
Installation of screed – 8%
Installation of elevators and adjustment – 70%
Roofing – 70%
Entrance group – 30%

Building No. 7
Plumbing works – 89%
Electric wiring works – 81%
Ventilation and smoke exhaust system – 85%
Low-current systems – 88%
Finishing of GUP – 83%
Installation of elevators and adjustment – 82%
Façade works – 98%
Brickworks on the roof – 1%
Roofing – 99%.
Entrance group – 99%
Development of adjoining territory – 62%

RC “Parkovi Ozera”

Building No. 12
Decoration works inside apartments.

Building No. 13
Installation of walls, partitions, brickworks (internal) - 97%.
Installation of window structures - 96%
Plumbing works – 35%
Electric wiring works – 30%
Ventilation and smoke exhaust system – 19%
Low-current systems – 17%
Wall plastering – 31%
Installation of screed -27%
Installation of elevators and adjustment – 80%
Façade works – 54 %
Façade heat insulation 78%
Façade finishing – 58%
Roofing – 69%.
Entrance group – 42%

RC “Ozernyi Hai Gatne”

Building No.2
Internal decoration -98%
Development of adjoining territory -98%

Building No. 3
Development of adjoining territory – 99%.

Building No. 4
Internal decoration - 80%.

Building No. 5
Internal decoration - 77%.
Glazing – 96%
Façade – 95%

Building No.6
Monolith works :
Section 1: 2nd floor – 10%
Section 2: 2nd floor – 30%
Section 3: 2nd floor - 60%

RC “Traditsiya”

Building No.2
Active finishing works inside apartments.

Building No.4
Vertical structure element of the 7th floor, slab over the 6th floor are in progress.
Brickworks – 2nd floor and basement.

RC “Malakhit”

Building No.4
Section 401 – vertical element of the 22nd floor. Brickworks on 10--20 floors.
Sections 403 –  Finishing works – 2-8 floors.
Sections 405-406 – finishing works are ongoing: Section 404 final decoration (tiling, painting) – 1-13 floors. Section 405 –final decoration –1st to 13th floors. Section 406 –final decoration –1st to 13th floors. Façade works – 80%
Works on waterproofing of parking areas are ongoing. Development of promenade zone – 35%.

RC “Nyvky-Park”

Building No.3
Installation of window structures at the staircases of all sections is in progress.
Finishing works at GUP: s Г and Д – 8th floor.
Installation of external mains is in progress.
Works on installation of entrance groups are ongoing.
Roofing is in progress: works in section Д.
Installation of façade is in progress.
Works on development of adjoining territory are in progress.

Building No.4

Works on installation of window structures: section B – on the 17th floor.
Plastering works at GUP: section E – up to the 18th floor and section Б – on the 15th floor and section B – on the 16th floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Installation of screed – section Б – 17th floor, section B – on the 16th  floor.t
Finishing works and tiling at GUP: section Е – up to the 16th floor, section Б – on the 10th  floor, section В – on the 11th floor.

Building No.5
Installation of monolith frame
section A - slab over the 17h floor,
section E – slab over the 17th floor
section Б – slab over the 17th floor.
Brickworks on the floors 1, 5, 6, 7, 8, 9 of section A; section Е -
on the 8, 9 floors and basement. Section Б - on the 1, 2, 3, 4, 5 and 6 floors.
Water proofing of basements at sections А, Б and Е.
Back filling of the pit is in progress.

Building No.6
Installation of vertical elements of the 9th floor at section Г
Installation of the slab over the 8th floor at section E.
Installation of the slab over the 8th floor at section Д*
Brickworks on the 3d floor in section Г. 2, 3, 4 floors in section Е and 2, 3, 4 floors in section Д *.

Building No.8
Installation of the formwork and reinforcement of the basement slab in section Г *
Arrangement of chip basis at sections  Б  and B.

RC “Vidradnyi”

Building No.2
Decoration works inside “turn-key” apartments (4, 5, 7, 8, 10, 11, 12 13, 16 floors).

Building No.3
Roofing – 70%
Installation of metal and plastic windows - 95%.
Façades works are in progress  – 75% (works on the roof in cold passes)
Installation of cement and sand screed are in progress – 9, 15 floors.
Wall plastering on the 4, 5, 7 floors is in progress
Works on electric wiring and plumbing are in progress.
Works on installation of external mains are ongoing (К1, К2, ВК, gas supply line) .
Brickwork on the roof are in progress.

Building No.4
Installation of metal and plastic windows – 95%
Brickworks on the roof are in progress – 65%
Façades works are in progress – 70%
Installation of external mains (K1,K2,BK, gas supply line).
Works on electric wiring and plumbing are in progress.
Installation of cement and sand screed are in progress on the 6th floor is in progress.
Roofing is in progress.
Wall plastering – 17th and 18th floors.

Building No.5
Brickworks on the floors 9, 12, 16, basement and roof are in progress.
Works on installation of metal and plastic windows are ongoing – 70%.
Façade works - 10%
Installation of waterproof insulation on the basement – 50%.

RC “Teremky”

1st stage.
Completion of installation of windows up to the 25th floor.
Heat insulation of the building is in progress. Roofing works are ongoing. Painting of the façade is ongoing.
Internal mains and plumbing works are in progress.
Wall plastering of GUPs  on the 1st floor.
Pouring of screed  - 16-17 floors.
Stage 2, section 2 – Brickworks on the 25th floor are ongoing. Water-proofing of the basement is ongoing.
Stage 2, section 3 – water-proofing of the basement is ongoing.
Stage 3, section 4 - slab over the vertical elements of the 17th floor is completed. Brickworks  - 2nd to 9th floors.
Stage 3, section 5 – slab over the vertical elements of the 16th floor is in progress. Brickworks  - 7th to 8th floors.
Stage 3- section 6 – slab over the vertical elements of the 16th floor is in progress. Brickworks on 2nd to 5th floor are in progress.