PROGRESS OF CONSTRUCTION AS OF 30.08.18
PROGRESS OF CONSTRUCTION AS OF 30.08.18
30 august 2018
Progress of construction as of 30.08.18

RC "Volodymyrskyi"

Reinforcement and installation of vertical structures on the 19th floor.

Brickworks at the basement and on 2, 4, 6, 8 floors are ongoing. Works on installation of concealed low-current wiring on typical floors inside monolith structures are in progress.

Plastering works – 5th floor
Finishing of GUP – 5th floor

RC “Syretski Sady”

Building No. 1
Completion of installation of windows and balconies – 95%.
Plumbing works -2-5 floors/Electric wiring works – 2-10 floors
Plastering works – 3d floor.
Façade – heat insulation of walls has been commenced – 30%
Entrance groups – basements are completed

Building No. 2
Brickworks – 1st to 12th floor.

Building No. 3
Installation of frame structures – 1st to 10th floor.

Building No.4
Installation of frame structures – 1-16th floor
Brickworks – 1st to 8th floor

Building No.5
Piles are being tested.

RC “Yaskravyi”

Building No.6
Works on installation of walls, partitions, brickworks (external -81.7%, internal – 40.6%) are in progress.
Installation of window structures-43,9%
Plumbing works – 25,3%
Electric wiring works – 4%
Wall plastering – 1,8%
Installation of screed – 1,4%
Installation of elevators and adjustment – 70%
Roofing – 41,7%
Entrance group – 8,3%


Building No. 7
Plumbing works – 82%
Electric wiring works – 74%
Ventilation and smoke exhaust system – 79%
Low-current systems – 80%
Finishing of GUP – 73%
Installation of elevators and adjustment – 81%
Façade works – 87%
Brickworks on the roof – 1%
Roofing – covering of parapets, water drain pipes.
Entrance group – 60%
Development of adjoining territory – 25%


RC “Parkovi Ozera”

Building No. 12
Decoration works inside apartments.

Building No. 13
Installation of walls, partitions, brickworks (internal) - 93% (engineering recesses on 21st and 24th floors, intersection passes, engineering accesses in the basement).
Installation of window structures - 93% (adjustment of handles, windowsills)
Plumbing works – 33% (4-14 floors)
Electric wiring works – 22% (1-15 floors)
Ventilation and smoke exhaust system – 11%
Low-current systems – 17%(4-13 floors)
Wall plastering – 26%
Installation of screed -22% (3, 10 floors (cold passages)
Installation of elevators and adjustment – 80%
Façade works – 28%
Façade heat insulation 59%
Façade finishing – 30%
Roofing – 69%.
Entrance group – 42%


RC “Ozernyi Hai Gatne”

Building No.2
Internal decoration -89%
Development of adjoining territory -98%

Building No. 3
Development of adjoining territory – 99%.

Building No. 4
Internal decoration - 75%.

Building No. 5
Internal decoration - 55%.
Glazing – 91%
Façade – 85%

Building No.6
Monolith works :
1st section: basement – 50%, 1st floor – 20%
Installation and putting the tower cranes into operation– 95%.

RC “Traditsiya”

Building No.2
Plumbing – completion of works. Active finishing works inside apartments.

Building No.4
Vertical structure element on the 5th floor, slab over the 4th floor. Backfilling is in progress.

RC “Malakhit”

Building No.4
Section 401 – vertical element of the 19th floor. Brickworks on 1-15 floors.
Sections 402-403 – Plastering works – 2-6 floors.
Sections 405-406 – finishing works are ongoing: Section 404 final decoration (tiling, painting) – 1-8 floors. Section 405 –final decoration –1st to 13th floors. Section 406 –final decoration –1st to 13th floors. Façade works – 50%
Works on waterproofing of parking areas are ongoing. Development of promenade zone.

RC “Nyvky-Park”

Building No.3
Installation of window structures at the staircases of all sections is in progress.
Finishing works at GUP: section Г - on the 17th floor and section Д on the 16th floor.
Finishing works at GUP at section Ж are ongoing – on the 8th floor.

Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Roofing is in progress.
Installation of doors: section Г – 12th floor
Installation of façade is in progress.

Building No.4
Brickworks for walls: section B – on the 15th floor
Works on installation of window structures: section Б – on the 16th floor and section В – on the 14th floor.
Plastering works at GUP: section Б – on the 12th floor and section B – on the 14th floor.
Installation of external mains is in progress.
Installation of entrance groups is ongoing.
Installation of screed – section Б – 14th floor, section B – on the 8th floor.
Installation of internal engineering systems is in progress: section Б – 15th floor, section B – on the 15th floor.
Installation of elevators is ongoing.
Finishing works and tiling at GUP: section Е – up to 10th floor, section Б – 5th floor, section В – 7th floor.


Building No.5
Installation of monolith frame
section A slab over the 15h floor,
section E – slab over the 15th floor
section Б – vertical elements of the 15th floor.
Brickworks on the floors 1, 3, 4, 5, 6, 7 of section A; section Е -
on the 1, 4, 5, 6, 7 floors and basement. Section Б -
on the 2, 3, 4 and 6 floors
Water proofing of basements at sections А, Б and Е.
Back filling of the pit is in progress.

Building No.6
Installation of vertical elements of the 6th floor at section Г
Installation of vertical elements of the 6th floor at section E.
Installation of slab over the 5th floor at section Д*
Brickworks on the 2nd floor of section Г.

Building No.8
Excavation works on the pit are in progress.

RC “Vidradnyi”

Building No.2
Decoration works inside “turn-key” apartments (3,4, 5, 6, 7 8 and 16 floors).

Building No.3
Roofing - 70%
Installation of metal and plastic windows - 95%.
Façades works are in progress (painting) – 70%
Installation of cement and sand screed are in progress - 5, 11 floors.
Wall plastering on the 2, 3, 18 floors is in progress
Works on electric wiring and plumbing are in progress.
Works on installation of external mains are ongoing.
Brickworks on the roof are ongoing.

Building No.4

Installation of metal and plastic windows – 95%
Brickworks on the basement are in progress.
Façades works are in progress – 70%
Installation of external mains has been commenced.
Works on electric wiring and plumbing are in progress
Installation of cement and sand screed are in progress on the 2nd floor is in progress.



Building No.5
Brickworks on the floors 9, 10, 12, 13 and basement are in progress.
Works on installation of metal and plastic windows are ongoing.
Works on installation of façade have been commenced.


RC “Teremky”

1st stage.
Completion of installation of windows up to the 25th floor.
Heat insulation of the building is in progress. Roofing works are in progress. Plastering of façade is ongoing.
Internal mains and plumbing works are in progress.
Electric wiring – 24th floor. Plastering works -25th floor
Stage 2, section 2 – Brickworks on the 23nd to 25th floors are ongoing. Installation of windows – on the 16th floor.
Stage 2, section 3 – slabs over the vertical elements on the 25th floor.
Brickworks on the 22nd to 25th floors are ongoing. Installation of windows on the 17th floor.
Stage 3, section 4. Slab over the vertical elements of the 14th floor is completed.
Stage 3, section 5 – Slab over the vertical elements of the 13th floor is in progress.
Stage 3- section 6 – Slab over the vertical elements of the 12th floor is in progress.



Detailed photo reports of the construction progress are available on the websites of the complexes is sections “Gallery”.

Sincerely yours, Intergal-Bud Company